Stampede Solar (ERCOT-22INR0409) — Project Summary

Queue ID
ERCOT-22INR0409
Capacity
256.34 MW
Technology
Solar
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
Stampede Solar Project, LLC
IA Status
IA Executed

Stampede Solar

ERCOT-22INR0409BetaActiveSolarERCOTLBNL

256.34 MW generation in Hopkins, TX · In queue since November 2020 · Proposed COD February 2025

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

256.34 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

Signed Dec 2021

Interconnection

Queue → IA

1y 1m

IA → COD

3y 2m

Total Duration

1y 1m

Schedule

16 months past proposed COD

Construction75%
Queue EntryNov 5, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 15, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-02-10

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

Stampede Solar is a proposed solar generation project located in Hopkins County, Texas, with a total capacity of 256.34 MW. The developer is Stampede Solar Project, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-22INR0409, with an interconnection agreement executed on December 15, 2021. The queue entry date is November 5, 2020, and the proposed commercial operation date is February 10, 2025.

The proposed project is linked to the existing Stampede Solar Hybrid operating plant (EIA plant ID 67762). Recent news coverage of the project includes topics related to industry, regulatory matters, and deals.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Stampede Solar Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1685 Farmersville - 11688 Thorn Tree ckt 1

Data Source

LBNL

DeveloperEnel North Americapv magazine USA · 2024-08-26
TransactionPPA±pv magazine USA · 2024-08-26
OfftakerNestlépv magazine USA · 2024-08-26
PPA structurePhysicalpv magazine USA · 2024-08-26
PPA term15 yearspv magazine USA · 2024-08-26
Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
STAM_SLR_ALL

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-03-26

View all articles

No Ask reports yet for this entity.

Ask about Stampede Solar
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.