Dragan Storage
408.3 MW generation in Comanche, TX · In queue since August 2020 · Proposed COD March 2030
408.3 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Facility Study
IA Phase
COD target: 2030
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-31
Proposed commercial operation date per ERCOT interconnection queue
sourceThe Dragan Storage project is a proposed 408.3 MW battery storage project located in Comanche County, Texas. The developer is Hecate Grid Dragan Storage LLC. It is interconnected to the ERCOT grid under queue ID ERCOT-22INR0400, with an interconnection queue entry date of August 21, 2020. The proposed commercial operation date is February 28, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Dragan Storage project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hecate Grid Dragan Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1440 Comanche 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CPSES_UNIT1
- POI Substation
- Comanche Peak Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.