Old Aqueduct Batt
302.94 MW generation in Hale, TX · In queue since May 2020 · Proposed COD March 2030
302.94 MW
Capacity
1
Components
Battery
6y 6m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-01
Projected COD moved
8 times
Sep 2021 → Mar 2030
Net change
+102 months
first report to latest
Capacity
300 → 301 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/22INR0330/old-aqueduct-batt
- interconnection.fyi/project/ercot-22inr0330
- ercotqueue.com/project/22INR0330
- app.nrgmap.com/queues/ercot-22inr0330
- ercotqueue.com/developer/old-aqueduct-llc
Commercial operation date: Cleanview lists the project as 'Expected online 2028' and an interconnection.fyi snippet gives a 'proposed completion date ... May 31, 2028', versus LBNL's 2030-03-01. Both are queue aggregators rather than developer statements, and another interconnection.fyi excerpt still shows March 1, 2030, so the 2028 date is weakly supported.
Developer: Every source (LBNL, interconnection.fyi, ercotqueue.com) names only Old Aqueduct LLC, a single-project developer entity. No press release or article identifies a parent or operating company.
Status: LBNL, interconnection.fyi, and NRG Map (active as of 1 Sept 2026) all show the queue position as active. One aggregator (interxdata) labels it 'operational', which conflicts with the other sources and the lack of any IA or construction news, so I disregarded it.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Old Aqueduct Batt project is a proposed 302.94 MW battery storage project located in Hale County, Texas. The developer is Old Aqueduct LLC. It is interconnected to the ERCOT grid under queue ID ERCOT-22INR0330, with an interconnection queue entry date of May 1, 2020. The proposed commercial operation date is June 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Old Aqueduct Batt project has been mentioned in recent news coverage related to the grid and energy industry.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hale
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Old Aqueduct LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23920 Blackwater 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Blackwater HVDC Tie
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.