Pink Solar
151.9 MW generation in Hunt, TX · In queue since January 2020 · Proposed COD July 2029
151.9 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Phase
Signed Aug 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
6y 11m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2029-07-31
Projected COD moved
5 times
Oct 2022 → Jul 2029
Net change
+81 months
first report to latest
Capacity
151 → 152 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Hunt County permit request for 138 kV underground transmission line
apps.huntcounty.netInterconnection Agreement executed with ERCOT
apps.huntcounty.netResearch sources and reasoning (2 recorded sources)
low confidence at research time
- apps.huntcounty.net/minutes/LinkedDir/2022/Links%202022-08-23-Regular/17690.pdf
- interconnection.fyi/project/ercot-22inr0281
Commercial operation date: Only LBNL queue data provides a COD target of 2029-07-31. No news or press releases found discussing this specific utility-scale project's timeline.
Developer: LBNL lists Pink Solar, LLC as developer. No news coverage found for this utility-scale project. Note: search results surfaced an unrelated residential installer 'Pink Energy' (formerly PowerHome Solar) that went out of business in 2022, but this is a different entity from the Hunt County utility project.
Status: LBNL shows active status with IA executed in Aug 2022. Hunt County document from Aug 2022 confirms permit request for 138 kV underground transmission line, indicating project was advancing through local approvals at that time.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Pink Solar is a proposed solar generation project located in Hunt County, Texas, within the ERCOT region. The development project, with a total capacity of 151.9 MW, is listed in the ERCOT interconnection queue as entry ERCOT-22INR0281, with a queue entry date of January 30, 2020. The proposed commercial operation date is July 31, 2029.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the Pink Solar project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hunt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pink Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
971 Pruitt 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09