Sequoia II Solar (ERCOT-22INR0262) — Project Summary

Queue ID
ERCOT-22INR0262
Capacity
417.47 MW
Technology
Solar
Status
active
Location
Callahan, TX
Region
ERCOT
Developer
Deville Solar LLC
IA Status
IA Executed

Sequoia II Solar

ERCOT-22INR0262BetaActiveSolarERCOTLBNL + Live

417.47 MW generation in Callahan, TX · In queue since January 2020 · Proposed COD January 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

417.47 MW

Capacity

1

Components

Solar

6y 10m

In Queue

IA Executed

IA Phase

Signed Aug 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 7m

IA → COD

3y 5m

Total Duration

3y 7m

Construction75%
Queue EntryJan 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 29, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-01-28

Queue history
22INR0262 · 70 monthly ERCOT reports, Aug 2020 – Sep 2026

Projected COD moved

5 times

Jan 2023 → Jan 2027

Net change

+48 months

first report to latest

Capacity

550 → 417 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 22, 2020
Facilities study approvedMar 16, 2026
Interconnection agreement signedAug 29, 2023
On ERCOT's inactive listFeb 2022 – May 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 1, 2026
Differs from queue: Jan 28, 2027
Developer in saved assessment
Enbridge
Filed as Deville Solar LLC
Status at research time
Construction
IA executed (2023-08-29). Enbridge broke ground on the 815 MW Sequoia Solar project in Nov 2024 and phase one (~400 MW) is fully operational as of May 2026. Sequoia II appears to be the remaining phase, with EIA listing completion Dec 2026.
Financing
Not recorded

Milestones in this assessment

GroundbreakingNov 18, 2024Latest in this assessment

Enbridge broke ground on the 815 MW Sequoia Solar project in Callahan County, TX.

pv-magazine-usa.com
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. enbridge.com/stories/2026/may/sequoia-solar-phase-one-now-fully-operational
  2. electrek.co/2026/05/27/north-americas-largest-solar-farms-texas-sequoia-enbridge/
  3. pv-magazine-usa.com/2024/11/18/enbridge-breaks-ground-on-815-mw-sequoia-solar-project-in-texas/
  4. enbridge.com/stories/2024/december/sequoia-solar-project-renewable-energy-texas-power-purchase-at-and-t-toyota
  5. interconnection.fyi/eia/plant/69272
  6. cleanview.co/power-projects/planned/solar-farms/texas/22INR0262/sequoia-ii-solar

Commercial operation date: The EIA-based listing shows Enbridge Solar (Sequoia II), LLC with a proposed completion of December 1, 2026, and Cleanview also says 'Expected online 2026'. LBNL's 2027-01-28 is only about two months later, so the sources broadly agree. Phase one (about 400 MW) is already fully operational as of May 2026, which fits Sequoia II being the second phase.

Developer: LBNL lists the filing LLC 'Deville Solar LLC'. The EIA listing names the operator as 'Enbridge Solar (Sequoia II), LLC', and Enbridge's own pages describe the Sequoia Solar project in Callahan County, TX. The Enbridge-owned project LLC is the operating-company link.

Status: LBNL shows IA Executed and active. Project-wide groundbreaking in 2024 and completed phase one indicate the site is in construction. The snippets do not explicitly confirm Sequoia II's own construction progress, so this is an inference.

Project lifecycle
as of 2025-07-24
PhaseConstructionCarbonCredits.com · 2025-07-24
OperationalNoCarbonCredits.com · 2025-07-24
TechnologySolarCarbonCredits.com · 2025-07-24
DeveloperEnbridgeCarbonCredits.com · 2025-07-24
PPA offtakerMetaCarbonCredits.com · 2025-07-24

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Deville Solar is a proposed solar generation project with a total capacity of 425.02 MW. The project, located in Callahan County, Texas, is being developed by Deville Solar LLC. It consists of 425.02 MW of solar photovoltaic generation.

The project is listed in the ERCOT interconnection queue as entry ERCOT-22INR0262, with a queue entry date of January 22, 2020. Its proposed commercial operation date is November 21, 2026. An Interconnection Agreement (IA) has been executed for the project, with an IA date of August 29, 2023. The Point of Interconnection (POI) is the 68051 Reata 345kV substation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Callahan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Deville Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

68051 Reata 345kV

Data Source

LBNL + Live

DeveloperEnbridgeCarbonCredits.com · 2025-07-24
TransactionProject financingCarbonCredits.com · 2025-07-24
Deal value$900.0MCarbonCredits.com · 2025-07-24
OfftakerMetaCarbonCredits.com · 2025-07-24
PPA structurePhysicalCarbonCredits.com · 2025-07-24
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
ANCHOR_ALL

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.