Corazon Solar Phase II
203.9 MW hybrid in Webb, TX · In queue since December 2019 · Proposed COD June 2028
203.9 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Phase
Signed Aug 2020
Queue → IA
8 months
IA → COD
7y 10m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-06-01
- 2022-02·BayWa r.e.→Eni New Energy US / Eni Plenitudesource
BayWa r.e. completes sale of Corazon I and Guajillo storage to Eni New Energy US; Phase II likely included in portfolio
sourceThe Corazon Solar Phase II project is a proposed 203.9 MW solar generation project located in Webb County, Texas. The project, developed by BAYWA R.E. SOLAR PROJECTS, is in the ERCOT interconnection queue as entry ERCOT-22INR0257, with a queue entry date of December 19, 2019. The project's proposed commercial operation date is June 1, 2028.
The project has an Interconnection Agreement (IA) executed on August 4, 2020. The Point of Interconnection (POI) is the 80219 Lobo 345kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BAYWA R.E. SOLAR PROJECTS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80219 Lobo 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WFTANK_ESS1
- POI Substation
- Lobo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Corazon Solar Phase IIForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.