Corazon Solar Phase II
203.9 MW hybrid in Webb, TX · In queue since December 2019 · Proposed COD June 2028
203.9 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Phase
Signed Aug 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
8 months
IA → COD
7y 10m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-06-01
Projected COD moved
2 times
May 2022 → Jun 2028
Net change
+73 months
first report to latest
Capacity
204 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
- 2022-02·BayWa r.e.→Eni New Energy US / Eni Plenitudepv-magazine-usa.com
Milestones in this assessment
BayWa r.e. completes sale of Corazon I and Guajillo storage to Eni New Energy US; Phase II likely included in portfolio
pv-magazine-usa.comERCOT capacity charts confirm 2028 commercial operation target
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- ess-news.com/2025/01/13/eni-plenitude-completes-its-largest-battery-storage-project-in-texas/
- pv-magazine-usa.com/2022/02/25/baywa-r-e-completes-sale-of-its-corazon-i-solar-plant-and-guajillo-storage-project-to-eni-new-energy-us/
- energy-storage.news/eni-new-energy-buys-400mwh-texas-battery-storage-project-from-baywa-r-e/
- ercot.com/files/docs/2025/06/06/Capacity-Changes-by-Fuel-Type-Charts_May_2025.xlsx
- ercot.com/files/docs/2020/09/02/SARA-FinalFall2020.pdf
Commercial operation date: LBNL queue shows 2028-06-01 COD and ERCOT capacity charts confirm 2028 target. No contradicting news sources found; project remains in development with no updated timeline announcements.
Developer: LBNL filing shows BayWa r.e. as original developer. However, Eni New Energy US (now Eni Plenitude) acquired Corazon I and Guajillo storage from BayWa in Feb 2022. Phase II likely transferred in same portfolio deal or subsequent acquisition completed Jan 2025.
Status: LBNL shows 'active' status with IA executed in Aug 2020. ERCOT capacity charts as recent as May 2025 continue listing project as active with 2028 target. No withdrawal or cancellation signals found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Corazon Solar Phase II project is a proposed 203.9 MW solar generation project located in Webb County, Texas. The project, developed by BAYWA R.E. SOLAR PROJECTS, is in the ERCOT interconnection queue as entry ERCOT-22INR0257, with a queue entry date of December 19, 2019. The project's proposed commercial operation date is June 1, 2028.
The project has an Interconnection Agreement (IA) executed on August 4, 2020. The Point of Interconnection (POI) is the 80219 Lobo 345kV substation. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BAYWA R.E. SOLAR PROJECTS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80219 Lobo 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WFTANK_ESS1
- POI Substation
- Lobo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Corazon Solar Phase II
Data-driven briefing on Corazon Solar Phase II — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.