Shaula I Solar (ERCOT-22INR0251) — Project Summary

Queue ID
ERCOT-22INR0251
Capacity
205.2 MW
Technology
Solar+Battery
Status
active
Location
Dewitt, TX
Region
ERCOT
Developer
Shaula Energy Project, LLC
IA Status
IA Executed

Shaula I Solar

ERCOT-22INR0251BetaActiveSolarBatteryERCOTLBNL + Live

205.2 MW hybrid in Dewitt, TX · In queue since December 2019 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

205.2 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Executed

IA Phase

Signed Feb 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 2m

IA → COD

6y 4m

Total Duration

2y 2m

Construction75%
Queue EntryDec 3, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 16, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-06-15

Queue history
22INR0251 · 83 monthly ERCOT reports, Nov 2019 – Sep 2026

Projected COD moved

7 times

Jan 2022 → Jun 2028

Net change

+77 months

first report to latest

Capacity

205 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 3, 2019
Interconnection agreement signedFeb 16, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Oct 30, 2025
Differs from queue: Jun 15, 2028
Developer in saved assessment
BP
Filed as Shaula Energy Project, LLC
Status at research time
IA Executed
IA Executed — project remains active in queue with FIS pending; ERCOT capacity charts track it for 2025-2026 online date
Financing
Not recorded

Milestones in this assessment

IA executedFeb 16, 2022

Interconnection Agreement executed with ERCOT

interconnection.fyi
COD targetOct 30, 2025Latest in this assessment

Target COD per CPS Energy ERCOT capacity planning document

cpsenergy.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-22inr0251
  2. cpsenergy.com/content/dam/corporate/en/Documents/Infrastructure/omicron/Attachment-3-Need-ada-070225.pdf
  3. cpsenergy.com/content/dam/corporate/en/Documents/Infrastructure/sprucetopawnee/Attachment-3a-ERCOT-BD-Agenda-Item-10.1-040825-ada.pdf
  4. cleanview.co/power-projects/developers/bp
  5. ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx

Commercial operation date: LBNL shows 2026-03-31, but multiple ERCOT capacity reports (CPS Energy July 2025, ERCOT Board April 2024) consistently cite 10/30/2025 as the target COD. Most recent ERCOT chart (Dec 2025) shows 2026 without month precision, suggesting slippage is possible but 2025 Q4 remains the developer target.

Developer: LBNL filing entity is 'Shaula Energy Project, LLC' (project SPV). Cleanview's BP developer pipeline explicitly lists 'Shaula I Solar, 205 MW, Solar, Texas' under BP's projects, indicating BP is the parent/operating company behind the shell LLC.

Status: LBNL shows IA executed 2022-02-16 and status active. Multiple ERCOT planning documents (through Dec 2025) continue to track the project as planned capacity, confirming no withdrawal or suspension.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Shaula I Solar is a proposed 205.2 MW solar generation project located in Dewitt County, Texas. The project is being developed by Shaula Energy Project, LLC and is interconnected within the ERCOT region. It entered the ERCOT interconnection queue as project number ERCOT-22INR0251 on December 3, 2019, with a proposed commercial operation date of March 31, 2026.

The project's Interconnection Agreement (IA) was executed on February 16, 2022, and the project's interconnection point of interconnect (POI) is at tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1. The project is currently listed as "active" in the interconnection queue. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Dewitt

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Shaula Energy Project, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Elm Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.