Lamkin Solar (ERCOT-22INR0220) — Project Summary

Queue ID
ERCOT-22INR0220
Capacity
101.5 MW
Technology
Solar
Status
active
Location
Comanche, TX
Region
ERCOT
Developer
Commanche Solar, LLC
IA Status
IA Executed

Lamkin Solar

ERCOT-22INR0220BetaActiveSolarERCOTLBNL + Live

101.5 MW generation in Comanche, TX · In queue since June 2019 · Proposed COD August 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

101.5 MW

Capacity

1

Components

Solar

7y 1m

In Queue

IA Executed

IA Phase

Signed Mar 2025

Interconnection

Queue → IA

5y 9m

IA → COD

2y 5m

Total Duration

5y 9m

Construction75%
Queue EntryJun 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 6, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-08-08

Cross-source intelligence
Beta
Medium confidence·6 sources·as of 2026-06-01
Expected COD
2027-08-08
From queue filing
Developer
Commanche Solar, LLC
From queue filing
Status
IA Executed
IA Executed — interconnection agreement completed March 2025, project active with 2027 COD target, listed in ERCOT MORA February 2026 report
Financing
Unannounced
Key milestones
IA executedMar 6, 2025

Interconnection Agreement executed with ERCOT for Point of Interconnection in Comanche County

source
COD targetAug 8, 2027Most recent

Target commercial operation date listed in Texas Comptroller active agreements with $20M valuation

source
About

The Lamkin Solar project is a proposed 101.5 MW solar generation facility in Comanche County, Texas. Developed by Commanche Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0220, with a queue entry date of June 24, 2019. The proposed commercial operation date is August 8, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 69kV 258 Hamilton - 273 Gustine. The Lamkin Solar project has appeared in recent news coverage regarding renewable energy development in Texas.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Comanche

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Commanche Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 69kV 258 Hamilton - 273 Gustine

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Hamilton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.