Lamkin Solar
101.5 MW generation in Comanche, TX · In queue since June 2019 · Proposed COD November 2027
101.5 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Phase
Signed Mar 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 9m
IA → COD
2y 8m
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-11-08
Projected COD moved
4 times
Dec 2022 → Nov 2027
Net change
+59 months
first report to latest
Capacity
100 → 102 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT for Point of Interconnection in Comanche County
interchange.puc.texas.govTarget commercial operation date listed in Texas Comptroller active agreements with $20M valuation
comptroller.texas.govResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-22inr0220
- ercotqueue.com/project/22INR0220
- comptroller.texas.gov/economy/docs/active-list.xlsx
- ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
- interchange.puc.texas.gov/Documents/35077_2140_1500142.PDF
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1604741386902210/
Commercial operation date: LBNL proposed COD of 2027-08-08 is confirmed in multiple secondary sources (Texas Comptroller active agreements list, Facebook community post, local PDF). No contradictory dates found in research; IA executed March 2025 supports 2027 timeline.
Developer: All sources consistently identify 'Commanche Solar, LLC' as the developer with no parent company or operating entity mentioned. No evidence of shell-LLC structure or ownership by a larger developer.
Status: LBNL status 'active' with IA executed 2025-03-06 is confirmed by ERCOT queue tracker showing 'IA + FIS complete' and inclusion in ERCOT's Monthly Outlook for Resource Adequacy (MORA) February 2026 report.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Lamkin Solar project is a proposed 101.5 MW solar generation facility in Comanche County, Texas. Developed by Commanche Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0220, with a queue entry date of June 24, 2019. The proposed commercial operation date is August 8, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 69kV 258 Hamilton - 273 Gustine. The Lamkin Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Commanche Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 69kV 258 Hamilton - 273 Gustine
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Hamilton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.