Velociraptor Solar I (ERCOT-22INR0218) — Project Summary

Queue ID
ERCOT-22INR0218
Capacity
251.67 MW
Technology
Solar+Battery
Status
active
Location
Ector, TX
Region
ERCOT
Developer
Greyhound Solar 2
IA Status
Facility Study

Velociraptor Solar I

ERCOT-22INR0218BetaActiveSolarBatteryERCOTLBNL + Live

251.67 MW hybrid in Ector, TX · In queue since May 2019 · Proposed COD December 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

251.67 MW

Capacity

1

Components

Solar

7y 6m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

10y 7m

Facilities Study50%
Queue EntryMay 14, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Queue history
22INR0218 · 89 monthly ERCOT reports, May 2019 – Sep 2026

Projected COD moved

4 times

Dec 2022 → Dec 2029

Net change

+84 months

first report to latest

Capacity

500 → 242 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 14, 2019

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2029
From queue filing
Developer in saved assessment
Greyhound Solar 2
From queue filing
Status at research time
Active
Active — Facility Study phase, no IA executed. Project has been in queue 84+ months with no public progress signals.
Financing
Not recorded

Milestones in this assessment

IA executedLatest in this assessment

No IA executed — project remains in Facility Study phase as of latest ERCOT data

interconnection.fyi
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-22inr0218
  2. ercotqueue.com/developer/greyhound-solar-2
  3. ercotqueue.com/leaderboard
  4. cleanview.co/power-projects/planned/solar-farms/texas/22INR0218/velociraptor-solar-i

Commercial operation date: Only LBNL provides a COD estimate (2029-12-01). No news or press releases found to validate or contradict this date. Project remains in early Facility Study phase with no IA executed.

Developer: LBNL lists 'Greyhound Solar 2' as developer. No press releases, corporate announcements, or ownership information found in search results. All aggregator sites mirror LBNL data without additional context on parent company or operating entity.

Status: LBNL status is 'active' with IA status at 'Facility Study'. No news of withdrawal, construction, or advancement found. Leaderboard data confirms 84-month queue duration with no IA.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Greyhound Solar 2 is a proposed 500 MW solar generation project located in Ector County, Texas. The developer is listed as Greyhound Solar 2. This project is in the ERCOT interconnection queue as entry ERCOT-22INR0218, with a queue entry date of May 14, 2019. The proposed commercial operation date is November 17, 2028. The project's interconnection agreement status is currently in the Facility Study phase.

The Greyhound Solar 2 project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Ector

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Greyhound Solar 2

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#10012 METEOR 5 Substation 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.