Velociraptor Solar I
251.67 MW hybrid in Ector, TX · In queue since May 2019 · Proposed COD December 2029
251.67 MW
Capacity
1
Components
Solar
7 years
In Queue
Facility Study
IA Phase
COD target: 2029
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Greyhound Solar 2 is a proposed 500 MW solar generation project located in Ector County, Texas. The developer is listed as Greyhound Solar 2. This project is in the ERCOT interconnection queue as entry ERCOT-22INR0218, with a queue entry date of May 14, 2019. The proposed commercial operation date is November 17, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The Greyhound Solar 2 project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greyhound Solar 2
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#10012 METEOR 5 Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTop solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.