Anchor Wind III (ERCOT-21INR0546) — Project Summary

Queue ID
ERCOT-21INR0546
Capacity
16 MW
Technology
Wind
Status
active
Location
Eastland, TX
Region
ERCOT
Developer
RANCHLAND WIND PROJECT LLC
IA Status
IA Executed

Anchor Wind III

ERCOT-21INR0546BetaActiveWindERCOTLBNL + Live

16 MW generation in Eastland, TX · In queue since December 2021 · Proposed COD December 2025

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

16 MW

Capacity

1

Components

Wind

4y 7m

In Queue

IA Executed

IA Phase

COD target: 2025

Interconnection

Total Duration

4 years

Schedule

6 months past proposed COD

Construction75%
Queue EntryDec 3, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2025-12-29

About

The Anchor Wind III project is a proposed 16 MW wind generation project located in Eastland County, Texas. Developed by Ranchland Wind Project LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-21INR0546. The project entered the interconnection queue on December 3, 2021, with a proposed commercial operation date of December 29, 2025.

The interconnection agreement for Anchor Wind III has been executed as of November 30, 2020. The point of interconnection is the 345 kV Aspire Station (68011). The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Eastland

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

RANCHLAND WIND PROJECT LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

345 kV Aspire Station (68011)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Anchor Wind III
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.