Yellow Viking Solar
170.86 MW generation in Somervell, TX · In queue since October 2020 · Proposed COD July 2027
170.86 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Phase
Signed Oct 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
4y 9m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-13
Projected COD moved
3 times
Dec 2022 → Jul 2027
Net change
+55 months
first report to latest
Capacity
289 → 171 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Hood County terminated tax abatement agreement; Somervell County approved extension per Facebook post
hcnews.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- hcnews.com/stories/countys-tax-abatement-agreement-with-yellow-viking-solar-farm-no-longer-active,65733
- cleanview.co/planned-solar-projects/TX/21INR0520/yellow-viking-solar
- interconnection.fyi/project/ercot-21inr0520
- aterio.io/insights/us-energy-projects/ep/yellow-viking-solar-project
- cleanview.co/power-projects/planned/solar-farms/texas/67222_1/yellow-viking-solar
- renewablesinfo.org/plant/67222-yellow-viking-solar
Commercial operation date: LBNL queue shows proposed COD of 2027-07-13. Multiple aggregator sites (Cleanview, powerplantsinfo) corroborate 2027 or October 2027 target. No press releases or financing announcements provide a more recent update.
Developer: All sources consistently identify Yellow Viking Development One, LLC as the developer. No parent company or operating entity identified in search results. Entity appears to be the actual developer, not a shell LLC.
Status: LBNL shows Active status with IA executed Oct 2022. Hood County News (Feb 2025) reports tax abatement agreement is no longer active, but this is a local incentive issue, not project cancellation. No withdrawal or suspension signals found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Viking Solar is a proposed 288.99 MW solar generation project located in Somervell County, Texas. The developer is Yellow Viking Development One, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-21INR0520, with an interconnection queue entry date of October 23, 2020. The proposed commercial operation date is July 13, 2027.
The project's interconnection agreement (IA) was executed on October 25, 2022. The point of interconnection (POI) is the ap 345kV 1900 Comanche Peak - 11886 Timberview Switch. Viking Solar has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Somervell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Yellow Viking Development One, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1900 Comanche Peak - 11886 Timberview Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26