Jayhawk Solar
101.5 MW generation in Mitchell, TX · In queue since August 2019 · Proposed COD October 2025
101.5 MW
Capacity
1
Components
Solar
7y 3m
In Queue
Facility Study
IA Phase
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-30
Projected COD moved
4 times
Feb 2022 → Oct 2025
Net change
+44 months
first report to latest
Capacity
102 MW
unchanged in the reports
Latest stage
Screening started
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Mitchell County public hearing notice for Jayhawk Solar Reinvestment Zone with Mitchell Solar III, LLC valued at $266M
co.mitchell.tx.usChapter 313 tax agreement terminated, project moved to inactive list
comptroller.texas.govResearch sources and reasoning (4 recorded sources)
high confidence at research time
- gem.wiki/Jayhawk_solar_farm
- comptroller.texas.gov/economy/development/prop-tax/ch313/docs/inactive-list.xlsx
- co.mitchell.tx.us/upload/page/9644/docs/2024/20240909%20-%20Notice%20of%20Public%20Hearing.pdf
- facebook.com/george.tyson.9822/posts/the-jayhawk-solar-facility-proposed-by-vistra-corp-the-parent-company-of-txu-wil/1175092529947599/
Commercial operation date: Project is cancelled per Global Energy Monitor (Feb 2026) and Texas Comptroller inactive list shows 'Agreement terminated'. LBNL proposed COD of 2025-10-30 is now moot.
Developer: LBNL filing entity is 'Renewable Energy Ventures, LLC'. Facebook post and Mitchell County tax documents identify Vistra Corp (parent of TXU) as the actual developer behind the Jayhawk Solar Facility. Mitchell Solar III, LLC also appears in county records as the tax agreement entity.
Status: While LBNL shows 'active' status in Facility Study phase, Global Energy Monitor explicitly states the project is 'cancelled' and Texas Comptroller's inactive list confirms the Chapter 313 tax agreement was terminated.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Jayhawk Solar is a proposed 101.5 MW solar generation project in Mitchell County, Texas, being developed by Renewable Energy Ventures, LLC. The development project consists of a single solar component and would connect to the grid operated by the Electric Reliability Council of Texas (ERCOT). Its proposed point of interconnection is a tap on the 345 kV 1030 Morgan – 76030 Gasconades transmission line.
The project entered the ERCOT interconnection queue on August 5, 2019, under queue ID ERCOT-21INR0414. Its interconnection agreement process is at the Facility Study stage, and its queue status is listed as suspended. The proposed commercial operation date is October 30, 2025. Jayhawk Solar has appeared in two recent news articles, one covering deals and one covering development activity.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Renewable Energy Ventures, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1030 Morgan - 76030 Gasconades
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MGSES_CT123
- POI Substation
- Morgan Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.