Jayhawk Solar
101.5 MW generation in Mitchell, TX · In queue since August 2019 · Proposed COD October 2025
101.5 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Facility Study
IA Phase
COD target: 2025
Total Duration
6y 2m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-30
The Jayhawk Solar project is a proposed 101.5 MW solar generation facility in Mitchell County, Texas. The project, developed by Renewable Energy Ventures, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-21INR0414, with a queue entry date of August 5, 2019. The proposed commercial operation date is October 30, 2025. The project's interconnection status is currently in the Facility Study phase, and it is slated to connect to the tap 345kV 1030 Morgan - 76030 Gasconades point of interconnection.
The Jayhawk Solar project has been the subject of recent news coverage, with three articles categorized as industry news and deals.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Renewable Energy Ventures, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1030 Morgan - 76030 Gasconades
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MGSES_CT123
- POI Substation
- Morgan Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Jayhawk SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.