Pecan Prairie South (ERCOT-21INR0371) — Project Summary

Queue ID
ERCOT-21INR0371
Capacity
130.71 MW
Technology
Solar
Status
active
Location
Leon, TX
Region
ERCOT
Developer
ConnectGen Operating LLC
IA Status
Facility Study

Pecan Prairie South

ERCOT-21INR0371BetaActiveSolarERCOTLBNL + Live

130.71 MW generation in Leon, TX · In queue since August 2019 · Proposed COD May 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

130.71 MW

Capacity

1

Components

Solar

7y 3m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

7y 9m

Facilities Study50%
Queue EntryAug 16, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-01

Queue history
21INR0371 · 86 monthly ERCOT reports, Aug 2019 – Sep 2026

Projected COD moved

9 times

Jun 2021 → May 2027

Net change

+71 months

first report to latest

Capacity

300 → 133 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 16, 2019
Facilities study approvedMar 13, 2026
Interconnection agreement signedFeb 21, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 4y 4m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activitytechnology_launchTotalEnergies.com · 2022-07-11

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2027
From queue filing
Developer in saved assessment
Repsol
Ownership change in saved research
Status at research time
Active
Active — construction started October 2025 per Repsol groundbreaking announcement
Financing
Secured
Repsol sold stake in 777MW US solar portfolio (including Pecan Prairie) to Stonepeak for $340M in April 2025
Ownership history
  1. —·ConnectGen Operating LLC→Repsolrenewablesnow.com

Milestones in this assessment

Financing closeApr 2025

Repsol sold stake in 777MW US solar portfolio to Stonepeak for $340M

renews.biz
GroundbreakingOct 2025

Repsol broke ground on 595-MW Pecan Prairie solar park in Leon County, Texas

renewablesnow.com
COD targetMay 1, 2027Latest in this assessment

LBNL proposed COD (no updated public target found)

Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. renewablesnow.com/news/repsol-breaks-ground-on-595-mw-solar-park-in-texas-1282594/
  2. renews.biz/100265/repsol-partners-with-stonepeak-on-us-renewables-portfolio/
  3. gem.wiki/Pecan_Prairie_South_Solar
  4. power-technology.com/marketdata/power-plant-profile-pecan-prairie-south-solar-pv-project-us/

Commercial operation date: LBNL proposes 2027-05-01 COD. No news sources provide an updated target date; Repsol's Oct 2025 groundbreaking announcement for the 595-MW 'Pecan Prairie' park mentions construction start but no specific COD. LBNL date stands as only available estimate.

Developer: LBNL filing lists 'ConnectGen Operating LLC' as developer. Multiple 2025-2026 news sources (Renewables Now, PV Tech, reNews) confirm Repsol owns and is developing the Pecan Prairie solar park in Leon County, TX, indicating acquisition or project transfer from ConnectGen.

Status: LBNL status is 'active' at Facility Study stage. Renewables Now (Oct 2025) reports Repsol broke ground on the 595-MW Pecan Prairie solar park in Leon County, confirming transition from planning to construction phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The HIP Solar Project is a proposed 137.6 MW solar generation project located in Leon County, Texas. The project, developed by ConnectGen Operating LLC, is in the ERCOT interconnection queue as entry ERCOT-21INR0371, with a queue entry date of August 16, 2019. The proposed commercial operation date is May 1, 2027, and the project's interconnection status is currently in the Facility Study phase.

The HIP Solar Project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Leon

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

ConnectGen Operating LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

CTT Yellow Wolf, bus # 79007

Data Source

LBNL + Live

CompanyTotalEnergiesTotalEnergies.com · 2022-07-11
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Hilltop Lakes Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.