Oystercatcher Solar (ERCOT-21INR0362) — Project Summary

Queue ID
ERCOT-21INR0362
Capacity
222.2 MW
Technology
Solar
Status
active
Location
Ellis, TX
Region
ERCOT
Developer
Oystercatcher Solar, LLC
IA Status
IA Executed

Oystercatcher Solar

ERCOT-21INR0362BetaActiveSolarERCOTLBNL + Live

222.2 MW generation in Ellis, TX · In queue since May 2019 · Proposed COD January 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

222.2 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Executed

IA Phase

Signed Aug 2021

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 3m

IA → COD

5y 5m

Total Duration

2y 3m

Construction75%
Queue EntryMay 30, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 20, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-01-29

Queue history
21INR0362 · 82 monthly ERCOT reports, Dec 2019 – Sep 2026

Projected COD moved

9 times

Jun 2021 → Jan 2027

Net change

+67 months

first report to latest

Capacity

220 → 198 MW

changed in the reports

Latest stage

Energized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 30, 2019
Facilities study approvedNov 13, 2025
Interconnection agreement signedAug 20, 2021
Approved for energizationSep 2, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 4 years ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activityEPC awardedAssociated Construction Publications · 2022-11-20

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2026
Differs from queue: Jan 29, 2027From queue filing
Developer in saved assessment
Oystercatcher Solar, LLC
From queue filing
Status at research time
Construction
Construction — McCarthy Building Companies clearing and construction underway as of Feb 2025, financing closed via Marathon Capital
Financing
Secured
Construction financing closed for 194 MWAC / 252 MWDC project, advised by Marathon Capital, amount undisclosed

Milestones in this assessment

IA executedAug 20, 2021

ERCOT Standard Generation Interconnection Agreement executed

interchange.puc.texas.gov
Financing close2024

Construction financing closed, Marathon Capital advisor

marathoncapital.com
GroundbreakingFeb 2025

McCarthy Building Companies clearing and construction underway on 1200-acre site in Italy, TX

facebook.com
COD targetOct 28, 2026Latest in this assessment

Expected online 2026 per LBNL queue and third-party tracking

cleanview.co
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. marathoncapital.com/news-events/marathon-capital-advises-on-construction-financing-for-252-mwdc-oystercatcher-solar-project-in-ercot-n
  2. facebook.com/thelinrecycling/posts/oystercatcher-solar-crew-going-strong-for-mccarthy-building-companies-inc-cleari/1226956756098253/
  3. instagram.com/p/DGgz1MXJdYb/
  4. interchange.puc.texas.gov/Documents/52455_2_1158664.PDF
  5. cleanview.co/power-projects/planned/solar-farms/texas/21INR0362/oystercatcher-solar
  6. assets.comptroller.texas.gov/ch313/1896/1896-italy-oystercatcher-appamend1.pdf

Commercial operation date: LBNL queue shows proposed COD of 2026-10-28. Marathon Capital financing announcement and McCarthy Building construction activity in Feb 2025 confirm project is under construction, consistent with 2026 target, but no independent source provides a different specific COD.

Developer: All sources consistently identify 'Oystercatcher Solar, LLC' as both the legal entity and operating company. No parent company or shell-LLC structure is evident from available sources.

Status: LBNL shows 'Active' with IA Executed (Aug 2021). Marathon Capital announcement confirms financial close and start of construction. Feb 2025 social media posts show McCarthy Building actively clearing the 1200-acre Italy, TX site.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Oystercatcher Solar is a proposed 218.1 MW solar generation project located in Ellis County, Texas. The project, developed by Oystercatcher Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-21INR0362, with a queue entry date of May 30, 2019. The proposed commercial operation date is October 28, 2026.

The project's interconnection agreement was executed on August 20, 2021. The point of interconnection is the tap 345kV 1906 Venus - 68091 Navarro.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Ellis

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Oystercatcher Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 1906 Venus - 68091 Navarro

Data Source

LBNL + Live

DeveloperLightsource bpAssociated Construction Publications · 2022-11-20
EPC contractorMcCarthy Building CompaniesAssociated Construction Publications · 2022-11-20
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
DSWL_BES1
POI Substation
Venus Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.