Board Creek Wind (ERCOT-21INR0324) — Project Summary

Queue ID
ERCOT-21INR0324
Capacity
299.2 MW
Technology
Wind
Status
active
Location
Navarro, TX
Region
ERCOT
Developer
Limestone Wind Project, LLC
IA Status
IA Executed

Board Creek Wind

ERCOT-21INR0324BetaActiveWindERCOTLBNL + Live

299.2 MW generation in Navarro, TX · In queue since April 2019 · Proposed COD October 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

299.2 MW

Capacity

1

Components

Wind

7y 7m

In Queue

IA Executed

IA Phase

Signed Aug 2021

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 4m

IA → COD

5y 2m

Total Duration

2y 4m

Schedule

1 months past proposed COD

Construction75%
Queue EntryApr 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 19, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-10-31

Queue history
21INR0324 · 83 monthly ERCOT reports, Nov 2019 – Sep 2026

Projected COD moved

23 times

Oct 2021 → Oct 2026

Net change

+60 months

first report to latest

Capacity

301 → 299 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 24, 2019
Facilities study approvedApr 26, 2022
Interconnection agreement signedAug 19, 2021
Approved for energizationSep 19, 2022
Approved for synchronizationOct 6, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2026
From queue filing
Developer in saved assessment
—
From queue filing
Status at research time
Active
Active — IA executed August 2021, but project has experienced multi-year delays from original 2022 target
Financing
Not recorded

Milestones in this assessment

IA executedAug 19, 2021Latest in this assessment

Interconnection Agreement executed with ERCOT

interconnection.fyi
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-21inr0324
  2. cleanview.co/power-projects/planned/wind-farms/texas/21INR0324/board-creek-wind
  3. cleanview.co/planned-wind-projects/texas/21INR0324/board-creek-wind
  4. ercot.com/files/docs/2022/06/08/Capacity_Changes_by_Fuel_Type_Charts_May_2022_PlannedMonthly.xlsx

Commercial operation date: LBNL queue shows July 2026 COD. Cleanview aggregator shows February 2026 and generic 2026 dates. ERCOT planning document from June 2022 listed 2022 as target year, indicating significant historical slippage. Current consensus is 2026 but month uncertain.

Developer: Only LBNL filing entity 'Limestone Wind Project, LLC' is available. No press releases, corporate announcements, or news coverage identify the parent/operating company behind this project LLC.

Status: LBNL shows active status with executed interconnection agreement from 2021. Historical ERCOT planning documents show the project was originally targeting 2022, indicating substantial delays but no withdrawal.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Board Creek Wind project is a proposed wind generation facility with a total capacity of 299.2 MW. Located in Navarro County, Texas, the project is being developed by Limestone Wind Project, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-21INR0324, with a queue entry date of April 24, 2019, and a proposed commercial operation date of April 30, 2026. The project's Interconnection Agreement (IA) was executed on August 19, 2021.

The point of interconnection (POI) is the 345kV 3386 Outlaw Switch. The Board Creek Wind project has been the subject of recent news coverage, with 72 articles related to its development, regulatory status, and industry impact.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Navarro

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Limestone Wind Project, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

345kV 3386 Outlaw Switch

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.