Mountaineer Solar
332.1 MW generation in Brown, TX · In queue since April 2019 · Proposed COD September 2029
332.1 MW
Capacity
1
Components
Solar
7y 7m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
Projected COD moved
13 times
Dec 2021 → Sep 2029
Net change
+93 months
first report to latest
Capacity
332 → 329 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-21inr0294
- cleanview.co/power-projects/planned/solar-farms/texas/21INR0294/mountaineer-solar
- ercotqueue.com/project/21INR0294
- interxdata.com/projects/mountaineer-solar-ercot-gis-report-21inr0294/
- opencorporates.com/companies/us_tx/0803321288
Commercial operation date: Only the LBNL/ERCOT queue date (2029-09-01) is available. interconnection.fyi repeats it as 'The proposed completion date is September 1, 2029' and Cleanview says 'Expected online 2029', but both appear to derive from the queue data, so they are not independent confirmation. No developer press release or news gives a financing-backed target.
Developer: Every source that names a developer (ERCOT queue trackers, Texas corporate registries) gives the filing LLC, Mustang Mountaineer Solar LLC. No press release or news identifies a parent or operating company, so I did not infer one.
Status: LBNL, interconnection.fyi and ercotqueue.com all show the project as active with no IA (ercotqueue.com gives a 13% build-chance). interxdata.com calls it 'operational', but that conflicts with the other sources and the 2029 proposed COD, so I treated it as a data error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Mountaineer Solar is a proposed solar generation project located in Brown County, Texas, with a total capacity of 329.64 MW. The project, developed by Mustang Mountaineer Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-21INR0294, with a queue entry date of April 16, 2019. The proposed commercial operation date is November 1, 2028, and the project's interconnection agreement status is currently Facility Study.
The Mountaineer Solar project has been the subject of recent news coverage, with nine articles appearing in industry, grid, and deals publications.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mustang Mountaineer Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1444 Brown 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BBSES_UNIT1
- POI Substation
- Big Brown Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.