Greyhound Solar (ERCOT-21INR0268) — Project Summary

Queue ID
ERCOT-21INR0268
Capacity
335.45 MW
Technology
Solar
Status
active
Location
Ector, TX
Region
ERCOT
Developer
Rockhound Solar 2, LLC dba "Greyhound Solar"
IA Status
IA Executed

Greyhound Solar

ERCOT-21INR0268BetaActiveSolarERCOTLBNL + Live

335.45 MW generation in Ector, TX · In queue since March 2019 · Proposed COD June 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

335.45 MW

Capacity

1

Components

Solar

7y 8m

In Queue

IA Executed

IA Phase

Signed Jan 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 10m

IA → COD

4y 5m

Total Duration

2y 10m

Schedule

5 months past proposed COD

Construction75%
Queue EntryMar 28, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 15, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-06-30

Queue history
21INR0268 · 91 monthly ERCOT reports, Mar 2019 – Sep 2026

Projected COD moved

8 times

Jun 2021 → Jun 2026

Net change

+60 months

first report to latest

Capacity

740 → 335 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 28, 2019
Facilities study approvedOct 31, 2024
Interconnection agreement signedJan 15, 2022
Approved for energizationNov 26, 2025
Approved for synchronizationApr 24, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 30, 2026
From queue filing
Developer in saved assessment
Origis Energy
Filed as Rockhound Solar 2, LLC dba "Greyhound Solar"
Status at research time
Online
LBNL shows 'active' and not operational, but ercotqueue.com lists the project as commissioned and the Origis Rockhound Complex has passed 1 GW operational. The owner LLC also filed an ERCOT/PUC Emergency Operations Plan in Aug 2025, which operating generators do. Adjacent phases E and F are separate queue entries.
Financing
Secured
The Origis project page lists portfolio-level Texas financings: a $545M financing and a $340M Crux tax equity investment. The snippet gives no dates and does not explicitly tie them to Greyhound A, so attribution is inferred.
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. origisenergy.com/project/greyhound-solar-a/
  2. ercotqueue.com/project/21INR0268
  3. ercotqueue.com/developer/rockhound-solar-2-llc-dba-greyhound-solar
  4. interchange.puc.texas.gov/Documents/58602_4_1541515.PDF
  5. interconnection.fyi/project/ercot-21inr0268

Commercial operation date: No source gives a specific post-LBNL COD. The only dated figure is the LBNL/interconnection.fyi proposed completion of 2026-06-30. ercotqueue.com lists the project as 'Currently Commissioned' and Origis reports its Rockhound Complex has reached 1 GW operational, so the actual COD is probably at or before this date.

Developer: The LBNL filer is a project LLC. Origis Energy hosts a 'Greyhound A Solar' project page as part of its Rockhound Complex in Ector County, which ties the LLC to Origis. No acquisition or ownership change was found.

Status: ercotqueue.com ('Currently Commissioned; build-chance 100%'), the developer's operational-complex announcement and the Aug 2025 PUC filing all point to an operating asset, so the LBNL queue status appears stale. None of these sources explicitly confirms an in-service date for this specific phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Greyhound Solar is a proposed solar generation project with a total capacity of 587.76 MW. The project, located in Ector County, Texas, is being developed by Rockhound Solar 2, LLC dba "Greyhound Solar". It consists of 587.76 MW of solar photovoltaic generation.

The project is listed in the ERCOT interconnection queue as entry ERCOT-21INR0268, with an original queue entry date of March 28, 2019. The proposed commercial operation date is March 31, 2026. The project's Interconnection Agreement (IA) has been executed as of January 15, 2022. The point of interconnection is Tap 345kV 11010 Wolf - 1018 Moss.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Ector

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Rockhound Solar 2, LLC dba "Greyhound Solar"

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 11010 Wolf - 1018 Moss

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
WHCCS2_CC2
POI Substation
Wolf Hollow Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.