Anson Solar Center, Phase III (ERCOT-21INR0247) — Project Summary

Queue ID
ERCOT-21INR0247
Capacity
200 MW
Technology
Solar
Status
active
Location
Jones, TX
Region
ERCOT
Developer
Anson Solar Center 3, LLC
IA Status
Facility Study

Anson Solar Center, Phase III

ERCOT-21INR0247BetaActiveSolarERCOTLBNL + Live

200 MW generation in Jones, TX · In queue since June 2017 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200 MW

Capacity

1

Components

Solar

9y 5m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

11 years

Facilities Study50%
Queue EntryJun 23, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Queue history
21INR0247 · 92 monthly ERCOT reports, Jan 2019 – Sep 2026

Projected COD moved

4 times

Jun 2021 → Jun 2028

Net change

+84 months

first report to latest

Capacity

200 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 23, 2017

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jun 2028
From queue filing
Developer in saved assessment
ENGIE North America
Filed as Anson Solar Center 3, LLC
Status at research time
Active
Active — Facility Study stage, no construction announcements yet. Appears to be part of ENGIE's multi-phase Anson portfolio development.
Financing
Not recorded

Milestones in this assessment

IA executedJun 2017Latest in this assessment

Entered ERCOT interconnection queue as 21INR0247

cleanview.co
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. prnewswire.com/news-releases/engie-and-meta-announce-new-200-mw-renewable-energy-agreement-expanding-existing-relationship-to-meet-growing-power-demand-302348660.html
  2. pv-tech.org/engie-meta-ink-200mw-solar-pv-eapa-in-texas/
  3. esgtoday.com/meta-buys-100-of-renewable-energy-from-new-900-million-texas-solar-project/
  4. cleanview.co/power-projects/planned/solar-farms/texas/21INR0247/anson-solar-center-phase-iii
  5. lightsourcebp.com/us/news/check-presentation-job-fair-kick-off-jones-city-solar-project-in-texas/

Commercial operation date: LBNL queue shows June 2028 COD. No independent news sources mention Phase III specifically or provide alternative dates. All search results reference Anson 2 (a separate 200MW project with Meta PPA announced Jan 2025), not Phase III.

Developer: LBNL filing uses project LLC 'Anson Solar Center 3, LLC'. Multiple sources (PR Newswire, PV Tech, ESG Today) confirm ENGIE operates the Anson solar portfolio in Jones County, including the operational Anson 2 project. Phase III appears to be part of ENGIE's Anson development series.

Status: LBNL status is 'active' at Facility Study stage. No news coverage specific to Phase III construction or milestones found. Anson 2 (separate project) is operational with Meta PPA, suggesting ENGIE is developing phases sequentially.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Anson Solar Center, Phase III is a proposed 200 MW solar generation project located in Jones County, Texas. The developer is Anson Solar Center 3, LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-21INR0247, with a queue entry date of June 23, 2017, and a proposed commercial operation date of June 1, 2028. Its interconnection status is currently in the Facility Study phase.

The Anson Solar Center, Phase III project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Jones

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Anson Solar Center 3, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 68000 WShack - 68001 Clayton

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.