Tulsita Solar (ERCOT-21INR0223) — Project Summary

Queue ID
ERCOT-21INR0223
Capacity
256.2 MW
Technology
Solar
Status
active
Location
Goliad, TX
Region
ERCOT
Developer
Ray Ranch Solar LLC
IA Status
IA Executed

Tulsita Solar

ERCOT-21INR0223BetaActiveSolarERCOTLBNL + Live

256.2 MW generation in Goliad, TX · In queue since December 2018 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

256.2 MW

Capacity

1

Components

Solar

7y 11m

In Queue

IA Executed

IA Phase

Signed Sep 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 9m

IA → COD

4 years

Total Duration

3y 9m

Schedule

2 months past proposed COD

Construction75%
Queue EntryDec 5, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 19, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-09-15

Queue history
21INR0223 · 89 monthly ERCOT reports, May 2019 – Sep 2026

Projected COD moved

12 times

May 2021 → Sep 2026

Net change

+64 months

first report to latest

Capacity

258 → 256 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 5, 2018
Facilities study approvedMar 1, 2024
Interconnection agreement signedSep 19, 2022
Approved for energizationOct 22, 2024
Approved for synchronizationOct 30, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
May 30, 2026
Differs from queue: Sep 15, 2026From queue filing
Developer in saved assessment
Ray Ranch Solar LLC
Sources agreed at research time
Status at research time
Active
Active — IA executed September 2022, tax abatements approved, construction phase with $260M estimated value
Financing
Not recorded
Ownership history
  1. 2023-04·Tulsita Solar, LLC→Ray Ranch Solar LLCassets.comptroller.texas.gov

Milestones in this assessment

Permit approvedSep 14, 2022

Goliad County commissioners approved 70% tax abatement for project

southtexasnews.com
IA executedSep 19, 2022

Interconnection Agreement executed per LBNL queue data

southtexasnews.com
COD targetMay 2026Latest in this assessment

Expected commercial operation date May 2026 per LBNL queue

cleanview.co
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. southtexasnews.com/goliad_advance_guard/news/commissioners-approve-two-solar-farm-tax-abatements/article_36de8a8c-346a-11ed-9f7f-97b3e098b9c6.html
  2. comptroller.texas.gov/economy/development/prop-tax/ch313/agreement-docs-details.php?id=1839
  3. assets.comptroller.texas.gov/ch313/1839/1839-goliad-tulsita-amendapp2.pdf
  4. construction.com/projects/dr-202200511033-tulsita-solar-project
  5. cleanview.co/planned-solar-projects/TX/21INR0223/tulsita-solar

Commercial operation date: LBNL proposed COD of May 2026 aligns with Cleanview's January 2026 estimate and Dodge Construction Network's 2021 bid date suggesting multi-year construction timeline. No contradictory recent sources found.

Developer: LBNL filing entity 'Ray Ranch Solar LLC' is the actual project developer. Texas Comptroller records confirm name change from 'Tulsita Solar, LLC' to 'Ray Ranch Solar LLC' in 2023, but no parent operating company identified in search results.

Status: LBNL status 'active' with IA executed in 2022 is consistent with Dodge Construction Network listing the project in 'Construction' action stage and county tax abatement approvals in September 2022.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Tulsita Solar is a proposed 256.2 MW solar generation project located in Goliad County, Texas. The developer is Ray Ranch Solar LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-21INR0223, with an original queue entry date of December 5, 2018. The proposed commercial operation date is May 30, 2026.

The project's interconnection agreement (IA) was executed on September 19, 2022. The point of interconnection (POI) is Tap 138kV 8590 Tuleta - 8595 Euler.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Goliad

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Ray Ranch Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 8590 Tuleta - 8595 Euler

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Tuleta Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.