Samson Solar 1
250 MW generation in Lamar, TX · In queue since November 2018 · Proposed COD December 2026
250 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Phase
Signed Aug 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 9m
IA → COD
6y 4m
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
Projected COD moved
24 times
Dec 2021 → Dec 2026
Net change
+60 months
first report to latest
Capacity
700 → 250 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2026-04·Invenergy (100%)→WEC Energy Group (80%) / Invenergy (20%)dailyenergyinsider.com
Milestones in this assessment
WEC Energy Group acquired 80% ownership interest
dailyenergyinsider.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- pv-tech.org/monarch-invenergy-us170-million-phase-two-samson-solar-energy-center/
- earth911.com/eco-tech/largest-solar-project-in-us/
- nsenergybusiness.com/projects/samson-solar-energy-center/
- dailyenergyinsider.com/innovation/38406-wec-energy-group-to-acquire-80-percent-ownership-of-250-mw-texas-solar-center/
- prnewswire.com/news-releases/invenergy-powers-daily-life-with-largest-solar-project-in-the-us-301175733.html
- ketk.com/news/top-stories/severe-weather-destroys-solar-panels-in-lamar-county/
- ercot.com/files/docs/2023/08/04/Capacity-Changes-by-Fuel-Type-Charts_July_2023_PlannedMonthly.xlsx
Commercial operation date: News-extracted facts from Earth911 (2021-02-01) cite expected COD of 2023, and ERCOT planning chart from Aug 2023 lists 2023 as target year. LBNL's 2026-06-30 date is 3+ years later and appears stale given construction began in July 2020.
Developer: LBNL filing entity is 'Samson Solar Energy LLC' (project shell). News sources consistently identify Invenergy as the developer/operator, including PR Newswire announcement (Nov 2020) and PV Tech coverage. WEC Energy Group acquired 80% ownership interest per Daily Energy Insider (1 month ago), but Invenergy remains the operating developer.
Status: LBNL status 'active' with IA executed Aug 2020 is accurate for queue position. Construction began July 2020 per NS Energy, with 2023 COD target suggesting project is now online or substantially complete.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Samson Solar 1 project is a proposed 250 MW solar generation facility in Lamar County, Texas. Developed by Samson Solar Energy LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-21INR0221. The project entered the interconnection queue on November 20, 2018, and has a proposed commercial operation date of June 30, 2026. An Interconnection Agreement (IA) was executed on August 26, 2020.
The proposed project is linked to the existing Samson Solar Energy III LLC operating plant (EIA plant ID 63883). Recent news coverage indicates activity related to the project, with articles appearing in industry, regulatory, and deals categories.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Samson Solar Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap both 345kV 1685 FarmersVl - 1695 Moses ckts
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesSolar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Samson Solar Energy
Data-driven briefing on Samson Solar Energy — fleet, generation, financial, and news signals.
Samson Solar 1
Data-driven briefing on Samson Solar 1 — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.