Quantum Solar (ERCOT-21INR0207) — Project Summary

Queue ID
ERCOT-21INR0207
Capacity
321.66 MW
Technology
Solar+Battery
Status
active
Location
Haskell, TX
Region
ERCOT
Developer
IP QUANTUM II, LLC
IA Status
IA Executed

Quantum Solar

ERCOT-21INR0207BetaActiveSolarBatteryERCOTLBNL + Live

321.66 MW hybrid in Haskell, TX · In queue since September 2018 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

321.66 MW

Capacity

1

Components

Solar

8y 2m

In Queue

IA Executed

IA Phase

Signed Oct 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

5y 1m

IA → COD

2y 11m

Total Duration

5y 1m

Schedule

3 months past proposed COD

Construction75%
Queue EntrySep 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 26, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-09-01

Queue history
21INR0207 · 94 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

8 times

Dec 2021 → Sep 2026

Net change

+57 months

first report to latest

Capacity

313 → 322 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 27, 2018
Facilities study approvedJun 16, 2025
Interconnection agreement signedOct 26, 2023
Approved for energizationMar 6, 2026
Approved for synchronizationApr 10, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 22 months ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activitytechnology_launchDepartment of Energy (.gov) · 2025-01-15

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 1, 2026
From queue filing
Developer in saved assessment
Intersect Power
Filed as IP QUANTUM II, LLC
Status at research time
IA Executed
Active in the ERCOT queue with an IA executed 2023-10-26. No confirmed construction start or operation; the 2026 project financing report suggests development is advancing toward the 2026 COD target.
Financing
Secured
About $200M project financing from Hapoalim to Ashtrom, reported by The Jerusalem Post on 2026-03-09. The link to this specific project is inferred from the news extraction and not independently verified.

Milestones in this assessment

Financing closeMar 2026Latest in this assessment

Ashtrom reportedly secured ~$200M project financing from Hapoalim; linkage to Quantum Solar is unverified.

jpost.com
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. jpost.com/business-and-innovation/banking-and-finance/article-889723
  2. intersect.com/portfolio/quantum
  3. cleanview.co/power-projects/planned/solar-farms/texas/68760_IPQ1S/quantum-solar

Commercial operation date: LBNL lists a proposed COD of 2026-09-01. Cleanview's project page says 'Expected online 2026', which is consistent, and no source gives a different date. The DOE article's 'online' status is not credible for this project, since it is dated 2025-01 and appears to describe a different SB Energy/Google project.

Developer: The LBNL filer 'IP QUANTUM II, LLC' follows Intersect Power's project-LLC naming, and Intersect's own portfolio page lists a 'Quantum' Texas project co-located with data-center load. The news-extracted 'Ashtrom' (financing, March 2026) may be a co-owner or financing party, but no source confirms its role. The SB Energy/Google DOE item looks like a different project.

Status: LBNL shows active status with an executed IA and is_operational=false. Cleanview still lists the project as planned. The DOE 'online' signal conflicts with this and is discounted as likely belonging to another project.

Project lifecycle
as of 2025-01-15
PhaseOnlineDepartment of Energy (.gov) · 2025-01-15
OperationalYesDepartment of Energy (.gov) · 2025-01-15
TechnologySolarDepartment of Energy (.gov) · 2025-01-15
DeveloperSB EnergyDepartment of Energy (.gov) · 2025-01-15
PPA offtakerGoogleDepartment of Energy (.gov) · 2025-01-15
COD achievedReportedDepartment of Energy (.gov) · 2025-01-15

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Quantum Solar is a proposed 374.4 MW solar generation project located in Haskell County, Texas. The developer is IP QUANTUM II, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0207, with a queue entry date of September 27, 2018, and a proposed commercial operation date of June 1, 2026. The interconnection agreement (IA) was executed on October 26, 2023.

The proposed project is linked to the existing Quantum Solar operating plant (EIA ID 68760). Recent news coverage of the project includes 11 articles categorized as industry news, 2 about deals, and 1 about regulatory matters.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Haskell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

IP QUANTUM II, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

60089 Kilby Station 345kV

Data Source

LBNL + Live

DeveloperAshtromThe Jerusalem Post · 2026-03-09
PartnerGoogleDepartment of Energy (.gov) · 2025-01-15
CompanySB EnergyDepartment of Energy (.gov) · 2025-01-15
TransactionProject financingThe Jerusalem Post · 2026-03-09
Deal value$200.0MThe Jerusalem Post · 2026-03-09
LenderHapoalimThe Jerusalem Post · 2026-03-09
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
HIGH
Nearest Node (Estimated)
RN_QTUM_SLR
POI Substation
Solara Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.