Quantum Solar
321.66 MW hybrid in Haskell, TX · In queue since September 2018 · Proposed COD September 2026
321.66 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Phase
Signed Oct 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 1m
IA → COD
2y 11m
Total Duration
5y 1m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2026-09-01
Projected COD moved
8 times
Dec 2021 → Sep 2026
Net change
+57 months
first report to latest
Capacity
313 → 322 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Ashtrom reportedly secured ~$200M project financing from Hapoalim; linkage to Quantum Solar is unverified.
jpost.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- jpost.com/business-and-innovation/banking-and-finance/article-889723
- intersect.com/portfolio/quantum
- cleanview.co/power-projects/planned/solar-farms/texas/68760_IPQ1S/quantum-solar
Commercial operation date: LBNL lists a proposed COD of 2026-09-01. Cleanview's project page says 'Expected online 2026', which is consistent, and no source gives a different date. The DOE article's 'online' status is not credible for this project, since it is dated 2025-01 and appears to describe a different SB Energy/Google project.
Developer: The LBNL filer 'IP QUANTUM II, LLC' follows Intersect Power's project-LLC naming, and Intersect's own portfolio page lists a 'Quantum' Texas project co-located with data-center load. The news-extracted 'Ashtrom' (financing, March 2026) may be a co-owner or financing party, but no source confirms its role. The SB Energy/Google DOE item looks like a different project.
Status: LBNL shows active status with an executed IA and is_operational=false. Cleanview still lists the project as planned. The DOE 'online' signal conflicts with this and is discounted as likely belonging to another project.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Quantum Solar is a proposed 374.4 MW solar generation project located in Haskell County, Texas. The developer is IP QUANTUM II, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0207, with a queue entry date of September 27, 2018, and a proposed commercial operation date of June 1, 2026. The interconnection agreement (IA) was executed on October 26, 2023.
The proposed project is linked to the existing Quantum Solar operating plant (EIA ID 68760). Recent news coverage of the project includes 11 articles categorized as industry news, 2 about deals, and 1 about regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP QUANTUM II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60089 Kilby Station 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RN_QTUM_SLR
- POI Substation
- Solara Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.