Starr Solar Ranch
136.73 MW hybrid in Starr, TX · In queue since November 2018 · Proposed COD August 2025
136.73 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Phase
Signed Oct 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 11m
IA → COD
4y 10m
Total Duration
1y 11m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2025-08-14
Projected COD moved
9 times
Oct 2020 → Aug 2025
Net change
+58 months
first report to latest
Capacity
136 → 137 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
$348M financing package completed for 288MW Texas portfolio including Starr Solar
businesswire.comStarr Solar Farm and Second Division Solar Farm come online, 288MW portfolio operational
lightsourcebp.comFormal opening ceremony held in Starr County for operational solar farm
krgv.comResearch sources and reasoning (6 recorded sources)
high confidence at research time
- lightsourcebp.com/us/news/lightsource-bp-powers-up-288-megawatt-solar-portfolio-in-texas/
- businesswire.com/news/home/20240221400563/en/Lightsource-bp-Completes-%24348-Million-Financing-Package-for-Two-Utility-Scale-Solar-Projects-in-Texas
- krgv.com/news/solar-panel-farm-opens-in-starr-county/
- texasborderbusiness.com/starr-county-industrial-foundation-to-welcome-lightsource-bp-starr-solar-farm-march-26th/
- energy-oil-gas.com/news/texas-solar-power-expands-with-lightsource-bps-288mw-portfolio/
- solarbuildermag.com/projects/lightsource-bp-energizes-288-mw-solar-portfolio-in-texas-projects-weekly/
Commercial operation date: LBNL proposed COD was 2025-08-14, but Lightsource BP's official press release (Jan 31, 2025) and multiple trade publications confirm the project came online in January 2025, with a formal opening ceremony on March 26, 2025. The project achieved COD approximately 6 months ahead of the LBNL filing date.
Developer: LBNL filing entity 'Starr Solar Ranch 1 LLC' is a project SPV. Multiple sources (KRGV, Lightsource BP press release, Business Wire, Energy Oil & Gas) consistently identify Lightsource BP as the developer and operator. The $348M financing announcement (Feb 2024) was issued by Lightsource BP for this project.
Status: LBNL status shows 'active' with IA executed, but news sources confirm the project is now operational. Lightsource BP announced the 288MW portfolio (including Starr Solar) came online in January 2025, and local news covered the March 2025 opening ceremony.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Starr Solar Ranch is a proposed solar generation project located in Starr County, Texas, within the ERCOT region. The project, developed by Starr Solar Ranch 1 LLC, has a total capacity of 136.73 MW. It is listed in the ERCOT interconnection queue as entry 20INR0216, with an original queue entry date of November 7, 2018, and a proposed commercial operation date of August 14, 2025. The project's interconnection agreement was executed on October 1, 2020.
The proposed project is linked to the existing Starr Solar Ranch operating plant (EIA ID 65975). Recent news coverage has highlighted the project, with 15 articles appearing in industry, grid, and development publications.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Starr Solar Ranch 1 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8795 Roma 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- STAR_SLR_RN
- POI Substation
- Roma Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26