El Sauz Ranch
301.5 MW generation in Willacy, TX · In queue since June 2018 · Proposed COD December 2026
301.5 MW
Capacity
1
Components
Wind
8y 5m
In Queue
IA Executed
IA Phase
Signed Jan 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
5y 11m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-01
Projected COD moved
34 times
Sep 2021 → Dec 2026
Net change
+63 months
first report to latest
Capacity
302 → 302 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2021-12·Apex Clean Energy→JERA Americas (JERA Co.)businesswire.com
Milestones in this assessment
JERA Americas acquired 100% of the El Sauz wind project from Apex Clean Energy.
businesswire.comConstruction commenced on the roughly 300 MW El Sauz onshore wind project.
nsenergybusiness.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- businesswire.com/news/home/20211201006236/en/JERA-Americas-Acquires-El-Sauz-Wind-Project-in-Texas-from-Apex-Clean-Energy
- nsenergybusiness.com/projects/el-sauz-onshore-wind-power-project/
- askthegrid.com/assets/facilities/el-sauz-ranch-wind-llc
- infrasure.ai/plant/65760-el-sauz-ranch-wind-llc
- cleanview.co/power-projects/operating/wind-farms/texas/65760/el-sauz-ranch-wind-llc
Commercial operation date: askthegrid reports that EIA's May 2026 inventory lists one operating generator dated January 2025, and infrasure.ai says the facility 'began operating in 2025'. Cleanview also lists it as operating. LBNL's proposed COD of 2026-12-01 is about 1.9 years later than this. The 2022 news target of Q4 2022 was never met.
Developer: Business Wire (Dec 2021) says JERA Americas acquired a 100% interest in the project from Apex Clean Energy. NS Energy also names JERA Renewables as developer. The LBNL entity is the project shell LLC. A 2019 MyRGV article credited E.ON with announcing the project, but no source documents an E.ON ownership transfer, so it is not included in the history.
Status: Construction began in January 2022 (NS Energy). Cleanview, infrasure.ai and askthegrid (citing EIA) all list the plant as operating, so the LBNL 'active' status is stale.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The El Sauz Ranch project is a proposed 301.5 MW wind generation project located in Willacy County, Texas. Developed by El Sauz Ranch Wind, LLC, the project consists entirely of wind generation. It is interconnected within the ERCOT queue as entry ERCOT-20INR0097, with a queue entry date of June 19, 2018, and a proposed commercial operation date of March 16, 2026. The project's Interconnection Agreement (IA) was executed on January 27, 2021.
The proposed project is linked to the existing El Sauz Ranch Wind, LLC operating plant (EIA ID 65760). Recent news coverage has discussed the project in the context of industry developments.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Willacy
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
El Sauz Ranch Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8663 EL SAUZ POI 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ELSAUZ_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-19
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.