Fagus Solar Park 1 SLF
166.42 MW hybrid in Childress, TX · In queue since May 2018 · Proposed COD January 2026
166.42 MW
Capacity
1
Components
Solar
8y 6m
In Queue
IA Executed
IA Phase
Signed Feb 2019
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
9 months
IA → COD
6y 11m
Total Duration
9 months
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-01-14
Projected COD moved
11 times
Jul 2020 → May 2026
Net change
+70 months
first report to latest
Capacity
504 → 166 MW
changed in the reports
Latest stage
Commercial operation
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Aug 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Texas PUC lists project with January 2026 expected online date
ftp.puc.texas.govResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-20inr0091
- cleanview.co/planned-solar-projects/TX/20INR0091/fagus-solar-park-1-slf
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
- ercot.com/files/docs/2024/07/01/meter_point_provisional-approved_2026_02_04_1656.pdf
- ercotqueue.com/project/20INR0091
Commercial operation date: LBNL queue shows proposed COD of 2026-01-14. Multiple independent sources (Texas PUC, ERCOT dashboards, Cleanview) all confirm January 2026 target with no contradictory dates found in research.
Developer: LBNL filing uses 'Excel Advantage Services, LLC dba Misae Solar Park II' which appears to be a project-specific DBA. The parent operating company is Excel Advantage Services, with 'Misae Solar Park II' being the project brand name.
Status: LBNL shows 'active' status with IA executed since 2019. ERCOT meter point provisional approval document (July 2024) and multiple queue trackers confirm project remains active and on track for 2026.
About
Generated Apr 10, 2026 · Predates Aug 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Fagus Solar Park 1 SLF is a proposed solar generation project located in Childress County, Texas, with a total capacity of 166.42 MW. The project is being developed by Excel Advantage Services, LLC dba Misae Solar Park II. It consists of 166.42 MW of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-20INR0091, with an original queue entry date of May 15, 2018. The proposed commercial operation date is January 14, 2026. An Interconnection Agreement (IA) for the project was executed on February 21, 2019. The point of interconnection is the 60501 Tesla 345kV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Aug 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Childress
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Excel Advantage Services, LLC dba Misae Solar Park II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60501 Tesla 345kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FAGUSSLR_RN
- POI Substation
- Kirkland Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Fagus Solar Park 1 SLF
Data-driven briefing on Fagus Solar Park 1 SLF — fleet, generation, financial, and news signals.
Misae Solar
Data-driven briefing on Misae Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.