Baird North Wind
340 MW generation in Callahan, TX · In queue since May 2018 · Proposed COD December 2026
340 MW
Capacity
1
Components
Wind
8y 6m
In Queue
IA Executed
IA Phase
Signed May 2019
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 year
IA → COD
7y 7m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-31
Projected COD moved
11 times
Dec 2020 → Dec 2026
Net change
+72 months
first report to latest
Capacity
300 → 340 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2018-07·Chermac Energy→NorthRenew Energynorthrenew.com
- 2019·NorthRenew Energy→Clearway Energy Groupnorthrenew.com
Milestones in this assessment
NorthRenew obtained the right to purchase the Baird North project from Chermac Energy.
northrenew.comNorthRenew sold the project to Clearway, which renamed it Mesquite Sky Wind.
northrenew.comClearway achieved construction commencement on Mesquite Sky (f/k/a Baird North Wind).
northrenew.com$427M construction debt financing, led by a global lender group, announced alongside construction start.
northrenew.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- northrenew.com/northrenew-energys-mesquite-sky-wind-project-commences-construction/
- northrenew.com/northrenew-energy-obtains-right-to-purchase-278-mw-baird-north-project/
- renewatlas.com/project/baird-north-wf
- ercotqueue.com/project/20INR0083
- ercot.com/files/docs/2021/10/04/Historical_Temporary_Exemptions_2021_10_04_0810.pdf
Commercial operation date: NorthRenew's Jan 2021 release says Baird North Wind was renamed Mesquite Sky Wind, started construction, and expected to begin operations 'in late 2021'. RenewAtlas lists it as online since 2021 and ercotqueue.com shows it as 'Commissioned'. LBNL's 2026-12-31 is about 5 years stale.
Developer: Chermac Energy developed the project first. NorthRenew obtained the right to purchase it in July 2018 and sold it to Clearway in 2019. Clearway built it as Mesquite Sky Wind, while LBNL still lists the shell LLC BMP Wind, LLC. The news-extracted 'Invenergy' facts refer to other projects (Number Three Wind, Santa Rita East) and were discarded.
Status: Construction began in Jan 2021 with operations targeted for late 2021. RenewAtlas shows it online since 2021, ercotqueue.com shows it as commissioned, and ERCOT's Aug 2021 metering exemption for BAIRD NORTH WIND is consistent with energization. The LBNL 'active' status and 2026 COD reflect a stale queue record.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Baird North Wind project is a proposed 350 MW wind generation facility in Callahan County, Texas. Developed by BMP Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0083, with a queue entry date of May 4, 2018. The proposed commercial operation date is December 31, 2026. An Interconnection Agreement (IA) was executed on May 31, 2019.
The project has been the subject of recent news coverage, with three articles categorized as industry news and deals. The point of interconnection is the 68008 Latimer 345kV location.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Callahan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BMP Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68008 Latimer 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Latimer Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.