Baird North Wind (ERCOT-20INR0083) — Project Summary

Queue ID
ERCOT-20INR0083
Capacity
340 MW
Technology
Wind
Status
active
Location
Callahan, TX
Region
ERCOT
Developer
BMP Wind, LLC
IA Status
IA Executed

Baird North Wind

ERCOT-20INR0083BetaActiveWindERCOTLBNL + Live

340 MW generation in Callahan, TX · In queue since May 2018 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

340 MW

Capacity

1

Components

Wind

8y 6m

In Queue

IA Executed

IA Phase

Signed May 2019

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1 year

IA → COD

7y 7m

Total Duration

1 year

Construction75%
Queue EntryMay 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 31, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-31

Queue history
20INR0083 · 94 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

11 times

Dec 2020 → Dec 2026

Net change

+72 months

first report to latest

Capacity

300 → 340 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 4, 2018
Facilities study approvedOct 30, 2020
Interconnection agreement signedMay 31, 2019
Approved for energizationAug 9, 2021
Approved for synchronizationAug 20, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 3y 6m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneCOD achievedEnergy Global · 2023-05-08

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2021
Differs from queue: Dec 31, 2026
Developer in saved assessment
Clearway Energy Group
Ownership change in saved research
Status at research time
Online
LBNL shows 'active', but the project was built as Mesquite Sky Wind (about 345 MW, 69 Siemens Gamesa turbines) and appears to have been operating since about late 2021.
Financing
Secured
$427 million construction debt financing led by a lender group of global financial institutions, announced with construction commencement in Jan 2021.
Ownership history
  1. 2018-07·Chermac Energy→NorthRenew Energynorthrenew.com
  2. 2019·NorthRenew Energy→Clearway Energy Groupnorthrenew.com

Milestones in this assessment

Ownership changeJul 2018

NorthRenew obtained the right to purchase the Baird North project from Chermac Energy.

northrenew.com
Ownership change2019

NorthRenew sold the project to Clearway, which renamed it Mesquite Sky Wind.

northrenew.com
GroundbreakingJan 2021

Clearway achieved construction commencement on Mesquite Sky (f/k/a Baird North Wind).

northrenew.com
Financing closeJan 2021Latest in this assessment

$427M construction debt financing, led by a global lender group, announced alongside construction start.

northrenew.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. northrenew.com/northrenew-energys-mesquite-sky-wind-project-commences-construction/
  2. northrenew.com/northrenew-energy-obtains-right-to-purchase-278-mw-baird-north-project/
  3. renewatlas.com/project/baird-north-wf
  4. ercotqueue.com/project/20INR0083
  5. ercot.com/files/docs/2021/10/04/Historical_Temporary_Exemptions_2021_10_04_0810.pdf

Commercial operation date: NorthRenew's Jan 2021 release says Baird North Wind was renamed Mesquite Sky Wind, started construction, and expected to begin operations 'in late 2021'. RenewAtlas lists it as online since 2021 and ercotqueue.com shows it as 'Commissioned'. LBNL's 2026-12-31 is about 5 years stale.

Developer: Chermac Energy developed the project first. NorthRenew obtained the right to purchase it in July 2018 and sold it to Clearway in 2019. Clearway built it as Mesquite Sky Wind, while LBNL still lists the shell LLC BMP Wind, LLC. The news-extracted 'Invenergy' facts refer to other projects (Number Three Wind, Santa Rita East) and were discarded.

Status: Construction began in Jan 2021 with operations targeted for late 2021. RenewAtlas shows it online since 2021, ercotqueue.com shows it as commissioned, and ERCOT's Aug 2021 metering exemption for BAIRD NORTH WIND is consistent with energization. The LBNL 'active' status and 2026 COD reflect a stale queue record.

Project lifecycle
as of 2019-07-24
PhaseOnlineWindpower Engineering & Development · 2019-07-24
OperationalYesWindpower Engineering & Development · 2019-07-24
TechnologyWindWindpower Engineering & Development · 2019-07-24
DeveloperInvenergyWindpower Engineering & Development · 2019-07-24
PPA offtakerGrupo Bimbo, Merck, NovartisWindpower Engineering & Development · 2019-07-24
COD achievedReportedWindpower Engineering & Development · 2019-07-24

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Baird North Wind project is a proposed 350 MW wind generation facility in Callahan County, Texas. Developed by BMP Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0083, with a queue entry date of May 4, 2018. The proposed commercial operation date is December 31, 2026. An Interconnection Agreement (IA) was executed on May 31, 2019.

The project has been the subject of recent news coverage, with three articles categorized as industry news and deals. The point of interconnection is the 68008 Latimer 345kV location.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Callahan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BMP Wind, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

68008 Latimer 345kV

Data Source

LBNL + Live

DeveloperInvenergyEnergy Global · 2023-05-08
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Latimer Switchyard

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.