Baird North Wind (ERCOT-20INR0083) — Project Summary

Queue ID
ERCOT-20INR0083
Capacity
340 MW
Technology
Wind
Status
active
Location
Callahan, TX
Region
ERCOT
Developer
BMP Wind, LLC
IA Status
IA Executed

Baird North Wind

ERCOT-20INR0083BetaActiveWindERCOTLBNL + Live

340 MW generation in Callahan, TX · In queue since May 2018 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

340 MW

Capacity

1

Components

Wind

8y 2m

In Queue

IA Executed

IA Phase

Signed May 2019

Interconnection

Queue → IA

1 year

IA → COD

7y 7m

Total Duration

1 year

Construction75%
Queue EntryMay 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 31, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-31

Cross-source intelligence
Beta
Medium confidence·4 sources·as of 2026-06-01
Expected COD
2022
Queue date 3+ years staleQueue: 2026-12-31
Developer
NorthRenew Energy
Recent ownership change
Status
Active
Active — construction reportedly started March 2022 with target COD end of 2022, though current operational status unclear given ownership transition to NorthRenew
Financing
Unannounced
Ownership history
  1. ·BMP Wind, LLCChermac Energysource
  2. ·Chermac EnergyNorthRenew Energysource
Key milestones
Ownership change

NorthRenew Energy obtained right to purchase project from Chermac Energy

source
IA executedMay 31, 2019

Interconnection Agreement executed with ERCOT

source
COD target2022

Expected to be operational by end of 2022

source
GroundbreakingMar 30, 2022Most recent

Construction started on Baird North Wind Facility

source
About

The Baird North Wind project is a proposed 350 MW wind generation facility in Callahan County, Texas. Developed by BMP Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0083, with a queue entry date of May 4, 2018. The proposed commercial operation date is December 31, 2026. An Interconnection Agreement (IA) was executed on May 31, 2019.

The project has been the subject of recent news coverage, with three articles categorized as industry news and deals. The point of interconnection is the 68008 Latimer 345kV location.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Callahan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BMP Wind, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

68008 Latimer 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Latimer Switchyard

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.