Elbow Creek repower
— generation in Howard, TX · In queue since May 2018 · Proposed COD March 2027
—
Capacity
0
Components
8y 5m
In Queue
—
IA Status
Signed Nov 2007
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
IA → COD
19y 4m
Total Duration
8y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2027-03-31
The Elbow Creek repower is a proposed wind generation project in Howard County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The development project is being pursued by Elbow Creek Wind Project, LLC and is listed under queue identifier ERCOT-19INR0174. As a repowering effort, the project involves wind turbine technology. The available queue data does not specify a total capacity for the project.
The project entered the ERCOT interconnection queue on May 4, 2018, and currently holds an active status. Its proposed point of interconnection is the 1058 Longshore 345 kV substation. The queue record lists an interconnection agreement date of November 30, 2007, which predates the project's 2018 queue entry. The proposed commercial operation date is March 31, 2027.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Elbow Creek Wind Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1058 Longshore 345kV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- PC_NORTH_1
- POI Substation
- Longshore Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Elbow Creek repowerForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.