Cottonwood Bayou Solar (ERCOT-19INR0134) — Project Summary

Queue ID
ERCOT-19INR0134
Capacity
351.4 MW
Technology
Solar
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Cottonwood Bayou Solar, LLC
IA Status
IA Executed

Cottonwood Bayou Solar

ERCOT-19INR0134BetaActiveSolarERCOTLBNL + Live

351.4 MW generation in Brazoria, TX · In queue since September 2017 · Proposed COD October 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

351.4 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Phase

Signed Nov 2019

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 2m

IA → COD

6y 11m

Total Duration

2y 2m

Schedule

1 months past proposed COD

Construction75%
Queue EntrySep 22, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 13, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-10-30

Queue history
19INR0134 · 94 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

24 times

Nov 2020 → Oct 2026

Net change

+71 months

first report to latest

Capacity

150 → 351 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 22, 2017
Facilities study approvedApr 27, 2023
Interconnection agreement signedNov 13, 2019
Approved for energizationMay 1, 2024
Approved for synchronizationMay 29, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Sep 30, 2024
Differs from queue: Oct 30, 2026
Developer in saved assessment
TotalEnergies (50% sold to Apollo Funds)
Ownership change in saved research
Status at research time
Online
LBNL shows 'active' with IA executed, but the plant started commercial operations around Sept 2024 and is listed as operating by GEM (Feb 2026).
Financing
Secured
Apollo Funds acquired a 50% stake in a 2 GW Texas solar and BESS portfolio from TotalEnergies, announced 2024-12-04. The amount is not in the available snippet, and the portfolio's inclusion of Cottonwood is inferred.
Ownership history
  1. 2024-12·TotalEnergies (100%)→TotalEnergies / Apollo Funds (50/50, portfolio-level; inferred to include Cottonwood)ir.apollo.com

Milestones in this assessment

COD targetSep 30, 2024

TotalEnergies announced the start of commercial operations at Danish Fields and Cottonwood (actual start-up, not a target).

totalenergies.com
Ownership changeDec 4, 2024Latest in this assessment

Apollo Funds announced the acquisition of a 50% stake in a 2 GW Texas solar and BESS portfolio from TotalEnergies.

ir.apollo.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. totalenergies.com/newsroom/renewables-totalenergies-starts-its-largest-utility-scale-solar-farms-batteries/?lang=eng
  2. ir.apollo.com/news-events/press-releases/detail/528/apollo-funds-acquire-50-stake-in-2-gw-texas-solar-and-bess
  3. corporate.totalenergies.us/news/totalenergies-will-supply-lyondellbasell-through-two-long-term-solar-cppas
  4. gem.wiki/Cottonwood_Bayou_Solar

Commercial operation date: TotalEnergies' Sept 30, 2024 release says it 'has started commercial operations of Danish Fields and Cottonwood', and Global Energy Monitor (Feb 2026) lists Cottonwood Bayou as operating. LBNL's proposed COD of 2026-10-30 is about 2 years stale, and the Dec 2023 release had targeted end of 2024.

Developer: The LBNL filing entity is a project LLC owned and developed by TotalEnergies, per its CPPA and start-up releases. Apollo Funds announced a 50% stake in a 2 GW Texas solar and BESS portfolio from TotalEnergies in Dec 2024. The snippet does not name Cottonwood explicitly, so its inclusion in that portfolio is inferred.

Status: The TotalEnergies start-up announcement (Sept 2024) and the GEM operating listing (Feb 2026) both show the project is built and running. LBNL's 'active' status and non-operational flag reflect a stale queue record.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Cottonwood Bayou Solar is a proposed solar generation project with a total capacity of 351.4 MW, located in Brazoria County, Texas. The developer is Cottonwood Bayou Solar, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-19INR0134, with a queue entry date of September 22, 2017, and a proposed commercial operation date of May 29, 2026. The Interconnection Agreement (IA) was executed on November 13, 2019. The point of interconnection is tap 138kV 42870 Liverpool - 43070 Petson.

The proposed project is linked to the existing Cottonwood Bayou Solar operating plant (EIA plant ID 66915). The project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Cottonwood Bayou Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 138kV 42870 Liverpool - 43070 Petson

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
CTW_RN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.