Rodeo Solar
200 MW generation in Andrews, TX · In queue since June 2017 · Proposed COD November 2026
200 MW
Capacity
1
Components
Solar
9y 1m
In Queue
IA Executed
IA Phase
Signed Aug 2019
Queue → IA
2y 2m
IA → COD
7y 3m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-30
Rodeo Solar is a proposed 200 MW solar generation project located in Andrews County, Texas. The developer is Core Solar SPV I, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-19INR0103, with a queue entry date of June 29, 2017, and a proposed commercial operation date of November 30, 2026.
The project's Interconnection Agreement (IA) was executed on August 20, 2019. The point of interconnection is the 138kV 11273 NELSON SWITCH. Rodeo Solar has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Andrews
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Core Solar SPV I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV 11273 NELSON SWITCH
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Rodeo SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.