Monte Alto I
141.5 MW generation in Willacy, TX · In queue since November 2016 · Proposed COD June 2028
141.5 MW
Capacity
1
Components
Wind
10 years
In Queue
IA Executed
IA Phase
Signed Feb 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 3m
IA → COD
8y 4m
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2028-06-01
Projected COD moved
11 times
Dec 2019 → Jun 2028
Net change
+102 months
first report to latest
Capacity
200 → 142 MW
changed in the reports
Latest stage
Cancelled
last listed Apr 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
assets.comptroller.texas.govResearch sources and reasoning (3 recorded sources)
low confidence at research time
- assets.comptroller.texas.gov/ch313/1863/1863-lasara-monte-cert.pdf
- cleanview.co/power-projects/planned/wind-farms/texas/19INR0022/monte-alto-i
- mercomcapital.com/terra-gen-secures-383-million-financing-for-solar-project/
Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-06-01. No news or press releases found with updated COD targets; search results only returned weather data and unrelated content except for a 2022 Texas.gov document mentioning the project and Cleanview listing showing 2028 expected online date consistent with LBNL.
Developer: LBNL filing lists 'Terra-Gen' as developer, and Texas.gov document from 2022 confirms 'Terra-Gen Development Company' developing Monte Alto I Wind project. Recent Mercom article (Dec 2025) identifies Terra-Gen as 'independent renewable energy producer jointly owned by Igneo Infrastructure Partners and Masdar.'
Status: LBNL shows 'active' status with IA executed in February 2020. No news of construction start, withdrawal, or cancellation found. Cleanview listing confirms project as 'planned' with 2028 expected online date.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Monte Alto I project is a proposed 141.5 MW wind generation project located in Willacy County, Texas. Developed by Terra-Gen, it is interconnected within the ERCOT region under queue ID ERCOT-19INR0022. The project entered the interconnection queue on November 4, 2016, and has a proposed commercial operation date of June 1, 2028. An Interconnection Agreement (IA) was executed on February 13, 2020. The point of interconnection is at the tap 345kV 8318 Rio Hondo - 8383 N Edinburg.
The Monte Alto I project has been the subject of recent news coverage, with 35 articles mentioning the project. These articles primarily focus on deals within the energy industry.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Apr 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Willacy
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Terra-Gen
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 8318 Rio Hondo - 8383 N Edinburg
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Rio Hondo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.