Desert Sky repower (ERCOT-17INR0070) — Project Summary

Queue ID
ERCOT-17INR0070
Capacity
7.2 MW
Technology
Wind
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
DESERT SKY WIND FARM LLC
IA Status
IA Executed

Desert Sky repower

ERCOT-17INR0070BetaActiveWindERCOTLBNL + Live

7.2 MW generation in Pecos, TX · In queue since November 2017 · Proposed COD May 2023

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

7.2 MW

Capacity

1

Components

Wind

9 years

In Queue

IA Executed

IA Phase

Signed Oct 2018

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

11 months

IA → COD

4y 7m

Total Duration

11 months

Schedule

43 months past proposed COD

Construction75%
Queue EntryNov 8, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 18, 2018

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2023-05-16

Queue history
17INR0070 · 94 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

26 times

Mar 2019 → May 2023

Net change

+50 months

first report to latest

Capacity

7 MW

unchanged in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 8, 2017
Facilities study approvedFeb 6, 2018
Interconnection agreement signedOct 18, 2018
Approved for synchronizationSep 6, 2019

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Desert Sky repower is a proposed wind generation project located in Pecos County, Texas, with a total capacity of 7.2 MW. The developer is DESERT SKY WIND FARM LLC. The project is interconnected to two LCRA 138kV and is listed in the ERCOT interconnection queue as entry ERCOT-17INR0070, with a queue entry date of November 8, 2017. The proposed commercial operation date was May 16, 2023.

The project has an Interconnection Agreement (IA) executed on October 18, 2018. The project is currently listed as active in the interconnection queue. The Desert Sky repower has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

DESERT SKY WIND FARM LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

two LCRA 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.