Wake Solar
150 MW generation in Crosby, TX · In queue since July 2015 · Proposed COD December 2021
150 MW
Capacity
1
Components
Solar
11 years
In Queue
Facility Study
IA Phase
COD target: 2021
Total Duration
6y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
Wake Solar is a proposed 150 MW solar generation project located in Crosby County, Texas. The project, developed by Invenergy, entered the ERCOT interconnection queue as entry ERCOT-16INR0119 on July 20, 2015. Its interconnection status is currently in the Facility Study phase.
The project's status is listed as suspended. Wake Solar has been the subject of recent news coverage, with six articles appearing in industry, regulatory, and deals publications.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Crosby
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Invenergy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59904 Cottonwood 345kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Wake SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.