Mesteno Wind (ERCOT-16INR0081) — Project Summary

Queue ID
ERCOT-16INR0081
Capacity
201.6 MW
Technology
Wind
Status
active
Location
Starr, TX
Region
ERCOT
Developer
Mesteno Windpower, LLC
IA Status
IA Executed

Mesteno Wind

ERCOT-16INR0081BetaActiveWindERCOTLBNL + Live

201.6 MW generation in Starr, TX · In queue since December 2014 · Proposed COD March 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.6 MW

Capacity

1

Components

Wind

11y 11m

In Queue

IA Executed

IA Phase

Signed Apr 2018

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 4m

IA → COD

8y 11m

Total Duration

3y 4m

Construction75%
Queue EntryDec 30, 2014

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 25, 2018

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2027-03-01

Queue history
16INR0081 · 93 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

24 times

Nov 2019 → Mar 2027

Net change

+88 months

first report to latest

Capacity

202 MW

unchanged in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 30, 2014
Facilities study approvedJan 29, 2018
Interconnection agreement signedApr 25, 2018
Approved for energizationNov 26, 2019
Approved for synchronizationDec 12, 2019
On ERCOT's inactive listJan 2026 – Jan 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 7y 7m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneconstruction startedDuke Energy · 2019-04-11
Expected COD2019-12-31Duke Energy · 2019-04-11

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 2019
Differs from queue: Mar 1, 2027
Developer in saved assessment
Duke Energy Renewables
Filed as Mesteno Windpower, LLC
Status at research time
Online
Online — operational since December 2019, currently operated by CAMS under InfraRed Capital Partners ownership as of November 2025
Financing
Secured
Financing secured for construction completed in 2019; project subsequently sold to InfraRed Capital Partners (date and amount not disclosed in available sources)
Ownership history
  1. 2025-11·Duke Energy Renewables→InfraRed Capital Partnerslinkedin.com

Milestones in this assessment

IA executedApr 25, 2018

Interconnection Agreement executed with ERCOT

assets.comptroller.texas.gov
GroundbreakingApr 2019

Construction started by Duke Energy Renewables with Wanzek Construction as EPC contractor

news.duke-energy.com
COD targetDec 2019

Commercial operations commenced December 2019 with 56 Vestas V136 3.6 MW turbines

gridinfo.com
Ownership changeNov 2025Latest in this assessment

Project acquired by InfraRed Capital Partners, with CAMS providing asset management services

linkedin.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. news.duke-energy.com/releases/duke-energy-renewables-constructs-200-mw-mesteno-wind-project-in-texas
  2. gridinfo.com/plant/mesteno/62258
  3. linkedin.com/posts/brian-ivany-72945539_cams-broadens-wind-asset-management-portfolio-activity-7392332418382221312-Cuxk
  4. assets.comptroller.texas.gov/ch313/1271/rio-1271-mesteno-findings.pdf
  5. derivaenergy.com/projects/mesteno-wind-project/

Commercial operation date: Duke Energy press release from April 2019 announced construction start with expected COD end of 2019. GridInfo confirms operational December 2019. LBNL's 2025-06-30 proposed COD is 5+ years stale.

Developer: LBNL filing entity is 'Mesteno Windpower, LLC' (project shell). Duke Energy Renewables is the actual operating company that constructed and operated the project, confirmed by multiple press releases and operational records.

Status: GridInfo confirms operational December 2019. Recent November 2025 LinkedIn post shows CAMS providing asset management services, indicating active operations under new ownership.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Mesteno Wind project is a proposed 201.6 MW wind generation facility in Starr County, Texas. Developed by Mesteno Windpower, LLC, the project consists of 201.6 MW of wind capacity. It is interconnected within the ERCOT queue as entry ERCOT-16INR0081, with an interconnection agreement executed on April 25, 2018. The proposed commercial operation date is June 30, 2025.

The project is linked to the existing Mesteno operating plant (EIA ID 62258). The Mesteno Wind project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Starr

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Mesteno Windpower, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

80355 Del Sol 345kV

Data Source

LBNL + Live

DeveloperDuke Energy RenewablesDuke Energy · 2019-04-11
EPC contractorWanzek ConstructionDuke Energy · 2019-04-11
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
MESTENO_RN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-14

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.