Wi-Al3-199SB (EPE-Q25-LG-6-13-2) — Project Summary

Queue ID
EPE-Q25-LG-6-13-2
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
El Paso, TX
Region
West
Developer
—
IA Status
In Progress (unknown study)

Wi-Al3-199SB

EPE-Q25-LG-6-13-2BetaActiveSolarBatteryEPELBNL

199 MW hybrid in El Paso, TX · In queue since June 2025 · Proposed COD December 2029

BA: ERCONERC: TRERC: ERCOT

199 MW

Capacity

1

Components

Solar

1y 5m

In Queue

In Progress (unknown study)

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Study Phase

2025 Cluster

In Study38%
Queue EntryJun 13, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
2029
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active — early-stage queue position filed June 2025, interconnection study phase not yet determined
Financing
Not recorded

Milestones in this assessment

IA executedJun 13, 2025Latest in this assessment

Interconnection application filed with EPE for 199 MW solar+storage project

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of 2029-12-31. No independent sources found to validate or contradict this target date.

Developer: LBNL filing shows no developer entity. Live search returned no results identifying the project sponsor or operating company behind this queue position.

Status: LBNL status shows active with IA in progress. Recent queue date (June 2025) indicates this is a newly filed project with no public development activity yet.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Wi-Al3-199SB (queue ID EPE-Q25-LG-6-13-2) is a proposed hybrid solar and battery storage development project in El Paso County, Texas, in the western region of the United States. The project has a total capacity of 199 MW. Its listed components include a 199 MW solar facility, and the project is identified as pairing solar generation with battery storage, though a separate capacity for the battery component is not specified. The project would interconnect at the Alamo 115 kV Substation within the service territory of El Paso Electric Company.

The project entered the El Paso Electric (EPE) interconnection queue on June 13, 2025, and is part of the 2025 Cluster study phase. It has requested Network Resource Interconnection Service (NRIS). As of the latest data, the project's status is active, and its interconnection agreement status is listed as in progress, with the specific study stage not identified. The proposed commercial operation date is December 31, 2029.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

El Paso

Grid Region

Mountain West

Market

—

Developer

—

Utility

El Paso Electric Company

Entity

EPE

Service Type

NRIS

Point of Interconnection

Alamo 115 kV Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.