Ve-DL-195SB
195 MW hybrid in Dona Ana, NM · In queue since May 2025 · Proposed COD June 2028
195 MW
Capacity
1
Components
Solar
1y 6m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 1m
Study Phase
2025 Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Project entered EPE interconnection queue
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of June 2028. No independent news or press releases found to validate or contradict this date.
Developer: LBNL filing shows no developer entity. Project name 'Ve-DL-195SB' appears to be an internal designation. No press releases, corporate announcements, or news coverage found identifying the project sponsor.
Status: LBNL queue status is 'active' with interconnection study in progress. No news coverage or public announcements found to provide additional ground-truth status updates.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Ve-DL-195SB (queue ID EPE-Q25-LG-5-22) is a proposed hybrid solar-plus-battery development project in Doña Ana County, New Mexico, in the western United States. The project has a total capacity of 195 MW. Its listed components include 195 MW of solar generation, and its technology detail also identifies a battery storage element, though no separate battery capacity is specified. No developer is named in the available data.
The project is in the interconnection queue of El Paso Electric Company (EPE), which it entered on May 22, 2025, and its status is active. It is part of EPE's 2025 Cluster study phase and has requested both Network Resource Interconnection Service and Energy Resource Interconnection Service (NRIS/ERIS). The proposed point of interconnection is the Verde 115 kV Substation. Its interconnection agreement status is listed as in progress, with the specific study stage unknown. The proposed commercial operation date is June 1, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Dona Ana
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
NRIS/ERIS
Point of Interconnection
Verde 115 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.