VS75SB
75 MW hybrid in Dona Ana, NM · In queue since September 2022 · Proposed COD December 2026
75 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The VS75SB project is a proposed 75 MW hybrid solar and battery energy storage project located in Dona Ana County, New Mexico. The project consists of 75 MW of solar generation. It is in the El Paso Electric Company (EPE) interconnection queue as project EPE-LG-22-9-7, with a queue entry date of September 30, 2022, and a proposed commercial operation date of December 1, 2026. Its interconnection agreement (IA) status is currently listed as "IA Pending".
The project would interconnect to the Salopek-Vado 115kV line. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Dona Ana
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
NRIS
Point of Interconnection
Salopek-Vado 115kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about VS75SBForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.