SS100S
100 MW generation in El Paso, TX · In queue since September 2022 · Proposed COD October 2025
100 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Phase
COD target: 2025
Total Duration
3y 1m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-31
Interconnection Agreement executed per LBNL queue status
The SS100S project is a proposed 100 MW solar generation project located in El Paso County, Texas. The project, developed by El Paso Electric Company (EPE), entered the EPE interconnection queue on September 30, 2022, under queue ID EPE-LG-22-9-5. The proposed commercial operation date is August 29, 2025, and the interconnection agreement has been executed. The point of interconnection is the Seabeck-San Felipe 115kV line.
The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
NRIS
Point of Interconnection
Wicked 115 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SS100SForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.