CO100SB Project (EPE-LG-19-3-4) — Project Summary

Queue ID
EPE-LG-19-3-4
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Otero, NM
Region
West
Developer
—
IA Status
IA Executed

CO100SB Project

EPE-LG-19-3-4BetaActiveSolarBatteryEPELBNL

100 MW hybrid in Otero, NM · In queue since March 2019 · Proposed COD April 2027

BA: PNMNERC: WECCRC: RCW

100 MW

Capacity

1

Components

Solar

7y 8m

In Queue

IA Executed

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 1m

Construction75%
Queue EntryMar 27, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-04-01

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 1, 2027
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active — IA Executed as of queue filing, no public updates on construction timeline
Financing
Not recorded

Milestones in this assessment

IA executedLatest in this assessment

Interconnection Agreement executed per LBNL queue status

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of April 2027. No independent news or research sources found to validate or contradict this date.

Developer: LBNL snapshot shows null developer field. No press releases, corporate announcements, or news coverage found identifying the project sponsor or operating company.

Status: LBNL reports 'active' status with executed interconnection agreement. Absence of news coverage prevents validation of current ground reality beyond queue position.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The CO100SB Project is a proposed 100 MW hybrid solar and battery energy project located in Otero County, New Mexico. The project, under development by El Paso Electric Company (EPE), consists of 100 MW of solar generation capacity. It is interconnected to the El Paso Electric Company queue as project EPE-LG-19-3-4, with an initial queue entry date of March 27, 2019. The proposed commercial operation date is April 1, 2027.

The project's interconnection point is the Chaparral-Oro Grande 115KV Line. The interconnection agreement (IA) for the project has been executed. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

NM

County

Otero

Grid Region

Mountain West

Market

—

Developer

—

Utility

El Paso Electric Company

Entity

EPE

Service Type

NRIS

Point of Interconnection

Escondido 115 kV Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.