D150S Project (EPE-LG-17-9-1) — Project Summary

Queue ID
EPE-LG-17-9-1
Capacity
150 MW
Technology
Solar+Battery
Status
suspended
Location
Dona Ana, NM
Region
West
Developer
IA Status
IA Executed

D150S Project

EPE-LG-17-9-1BetaSuspendedSolarBatteryEPELBNL

150 MW hybrid in Dona Ana, NM · In queue since September 2017 · Proposed COD September 2020

BA: PNMNERC: WECCRC: RCW

150 MW

Capacity

1

Components

Solar

8y 10m

In Queue

IA Executed

IA Phase

COD target: 2020

Interconnection

Total Duration

3 years

Suspended75%
Queue EntrySep 6, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 18–30 months

Commercial Operation

Proposed COD: 2020-09-01

About

The D150S Project is a proposed 150 MW solar and battery hybrid project located in Dona Ana County, New Mexico. The project, developed by El Paso Electric Company (EPE), consists of 150 MW of solar generation. It is interconnected to the El Paso Electric Company system at the Diablo 115 kV Substation.

The project is listed in the EPE interconnection queue as EPE-LG-17-9-1, with an original queue entry date of September 6, 2017. The proposed commercial operation date is September 15, 2025, and the Interconnection Agreement (IA) has been executed. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

NM

County

Dona Ana

Grid Region

Mountain West

Market

Developer

Utility

El Paso Electric Company

Entity

EPE

Service Type

NRIS/ERIS

Point of Interconnection

Diablo 115 kV Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.