Duke-PP00004
74.9 MW generation in Darlington, SC · In queue since September 2024 · Proposed COD December 2027
74.9 MW
Capacity
1
Components
Solar
1y 10m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-30
Duke-PP00004 is a proposed solar generation project with a total capacity of 74.9 MW, located in Darlington County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It entered the interconnection queue on September 4, 2024, with a proposed commercial operation date of November 15, 2026. The interconnection agreement is currently in progress, with the specific study type unknown.
The point of interconnection for the project is the Robinson Plant - Florence, suggesting a link to the existing Robinson Nuclear Plant. This proposed project has appeared in recent news coverage regarding Duke Energy's renewable energy development plans in the Southeast region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
SC
County
Darlington
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Robinson Plant - Florence
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-PP00004Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.