Duke-FC100379
12 MW generation in Orange, FL · In queue since November 2025 · Proposed COD June 2026
12 MW
Capacity
1
Components
Gas
1 year
In Queue
In Progress (unknown study)
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7 months
Schedule
6 months past proposed COD
Study Phase
Cluster: 2025 Annual DEF FERC Cluster; Cluster Sub Group: Central
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Duke-FC100379 is a proposed 12 MW natural gas generation project located in Orange County, Florida, in the southeastern United States. The developer's identity has been masked in the interconnection queue records. The project would connect to the Duke Energy Florida transmission system at the Parkway 69 kV Substation. It has requested Network Resource Interconnection Service (NRIS).
The project entered the Duke Energy Florida interconnection queue on November 25, 2025, and currently holds active status. It has been assigned to the 2025 Annual DEF FERC Cluster, within the Central cluster sub-group. The interconnection agreement process is listed as in progress, though the specific study stage has not been identified. The proposed commercial operation date is June 1, 2026, roughly six months after the project's queue entry date.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Orange
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Service Type
NRIS
Point of Interconnection
Parkway 69 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.