Project Duke-977636 — Project Summary

Queue ID
Duke-977636
Capacity
1.5 MW
Technology
Hydro
Status
active
Location
Anson, NC
Region
Southeast
Developer
IA Status
Cluster Study

Duke-977636

Duke-977636BetaActiveHydroDukeLBNL

1.5 MW generation in Anson, NC · In queue since June 2025

1.5 MW

Capacity

1

Components

Hydro

11 months

In Queue

Cluster Study

IA Phase

Interconnection

Total Duration

11 months

Study Phase

2025 DISIS

Impact Study25%
Queue EntryJun 26, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NC

County

Anson

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Progress

Entity

Duke

Service Type

NRIS

Point of Interconnection

Blewett Hydro Station

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
No news available for this project.

No Ask reports yet for this entity.

Ask about Project Duke-977636
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.