Duke-961188
455 MW generation in Stokes, NC · In queue since June 2024
455 MW
Capacity
1
Components
Gas
2y 1m
In Queue
Cluster Study
IA Phase
Total Duration
2y 1m
Study Phase
2024 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-961188 is a proposed 455 MW gas-fired generation project located in Stokes County, North Carolina. The project is being developed by Duke and is interconnected with Duke Energy Carolinas. It entered the interconnection queue on June 20, 2024, and is currently in the Cluster Study phase of the interconnection process.
The project consists of 455 MW of gas-fired generation capacity. It is listed as an active project in the interconnection queue. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Stokes
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
NRIS
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-961188Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.