Duke-956340
110 MW generation in Sampson, NC · In queue since June 2024
110 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Duke-956340 is a proposed solar generation project with a total capacity of 110 MW, located in Sampson County, North Carolina. The developer is listed as Masked. The project is interconnected with Duke Energy Progress and is in the Duke Energy interconnection queue, with a queue entry date of June 26, 2024. Its interconnection status is currently in the Cluster Study phase.
The proposed project is located in the Southeast region and connects to the CLINTON - MT OLIVE 230KV point of interconnection.
Generated from interconnection queue and public data sources
State
NC
County
Sampson
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
CLINTON - MT OLIVE 230KV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-956340Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.