Project Duke-956244 — Project Summary

Queue ID
Duke-956244
Capacity
99 MW
Technology
Battery
Status
active
Location
Robeson, NC
Region
Southeast
Developer
Duke Energy Progress, LLC.
IA Status
Cluster Study

Duke-956244

Duke-956244BetaActiveBatteryDukeLBNL

99 MW storage in Robeson, NC · In queue since June 2024

BA: CPLENERC: SERCRC: VACS

99 MW

Capacity

1

Components

Battery

2y 1m

In Queue

Cluster Study

IA Phase

Interconnection

Total Duration

2y 1m

Study Phase

2024 DISIS

Impact Study25%
Queue EntryJun 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

Duke-956244 is a proposed 99 MW battery storage project located in Robeson County, North Carolina. The project, under development by Duke Energy Progress, LLC., entered the Duke Energy Progress interconnection queue on June 19, 2024. Its point of interconnection is the Weatherspoon Plant Substation at 230kV.

The project's interconnection status is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NC

County

Robeson

Grid Region

Southeast

Market

Developer

Duke Energy Progress, LLC.

Utility

Duke Energy Progress

Entity

Duke

Service Type

NRIS/ERIS

Point of Interconnection

Weatherspoon Plant Substation 230kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform