Queue ID
Duke-949286
Capacity
0.875 MW
Technology
Solar
Status
active
Location
Anderson, SC
Region
Southeast
Developer
IA Status
Cluster Study

Duke-949286

Duke-949286BetaActiveSolarDukeLBNL

0.875 MW generation in Anderson, SC · In queue since May 2024

BA: DUKNERC: SERCRC: VACS

0.875 MW

Capacity

1

Components

Solar

2 years

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

2 years

Impact Study25%
Queue EntryMay 28, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

Duke-949286 is a proposed solar generation project located in Anderson County, South Carolina, within the Duke Energy Carolinas service area. The project, sponsored by Duke, has a total capacity of 0.88 MW, consisting entirely of solar photovoltaic generation.

The project is currently listed as active in the Duke Energy Carolinas interconnection queue, with an entry date of May 28, 2024. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the IVA SS substation.

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Anderson

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Service Type

Point of Interconnection

IVA SS

Data Source

LBNL

Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No Ask reports yet for this entity.

Ask about Project Duke-949286
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.