Project Duke-923973 — Project Summary

Queue ID
Duke-923973
Capacity
275 MW
Technology
Solar
Status
active
Location
Richmond, NC
Region
Southeast
Developer
Masked
IA Status
IA Pending

Duke-923973

Duke-923973BetaActiveSolarDukeLBNL

275 MW generation in Richmond, NC · In queue since September 2023

BA: CPLENERC: SERCRC: VACS

275 MW

Capacity

1

Components

Solar

2y 10m

In Queue

IA Pending

IA Phase

Interconnection

Total Duration

2y 10m

Study Phase

2023 Solar + Procurement

In Study38%
Queue EntrySep 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Cross-source intelligence
Beta
Low confidence·0 sources·as of 2026-06-01
Expected COD
Developer
Status
Active
Active — IA Pending, queued September 2023, no public development updates available
Financing
Unannounced
Key milestones
IA executedSep 2023Most recent

Project entered Duke queue with IA Pending status

About

Duke-923973 is a proposed solar generation project with a total capacity of 275 MW, located in Richmond County, North Carolina. The development project, sponsored by a masked developer and interconnected with Duke Energy Progress, entered the Duke Energy interconnection queue on September 27, 2023. Its interconnection status is currently in the Cluster Study phase.

The project is planned to connect to the LAURINBURG - RICHMOND 230KV point of interconnection.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NC

County

Richmond

Grid Region

Southeast

Market

Developer

Masked

Utility

Duke Energy Progress

Entity

Duke

Service Type

Point of Interconnection

LAURINBURG - RICHMOND 230KV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project Duke-923973
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.