Duke-899759
136 MW generation in Catawba, NC · In queue since June 2023 · Proposed COD August 2028
136 MW
Capacity
1
Components
Gas
3y 1m
In Queue
IA Executed
IA Phase
COD target: 2028
Total Duration
5y 2m
Study Phase
2023 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2028-08-31
Duke-899759 is a proposed project in Catawba County, North Carolina, with a total capacity of 136 MW. The project, developed by Duke, is a gas-fired generation facility. It is interconnected to the Duke Energy Carolinas system at the Marshall Steam Station 230KV Switchyard.
The project entered the Duke Energy Carolinas interconnection queue on June 28, 2023. Its interconnection agreement (IA) status is currently listed as "IA Pending".
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Catawba
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
NRIS
Point of Interconnection
Marshall Steam Station 230KV Switchyard
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-899759Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.