Duke-899581
20 MW generation in Wayne, NC · In queue since June 2023
20 MW
Capacity
1
Components
Gas
3y 1m
In Queue
IA Executed
IA Phase
Total Duration
3y 1m
Study Phase
2023 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Commercial operation date not yet determined
Duke Energy Progress, LLC is proposing a 20 MW gas-fired generation project, identified as Duke-899581, in Wayne County, North Carolina. The project entered the Duke Energy Progress interconnection queue on June 28, 2023. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Lee Substation at 115 kV.
The proposed project consists of 20 MW of gas-fired generation capacity. The project is located in the Southeast region and is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Wayne
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
Lee Substation 115 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Duke Energy CHP at Clemson University
Data-driven briefing on Duke Energy — fleet, generation, financial, and news signals.
Analyze Duke Energy's full portfolio
Energy intelligence report generated by Ask.
NextEra vs Duke
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
NextEra vs Duke
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.