Duke-899433
6.26 MW generation in Montgomery, NC · In queue since June 2023
6.26 MW
Capacity
1
Components
Hydro
3y 5m
In Queue
Construction
IA Phase
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 5m
Study Phase
2023 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Duke-899433 is a proposed hydroelectric generation project with a total capacity of 6.26 MW, located in Montgomery County, North Carolina. The developer is Duke Energy Progress, LLC, and the point of interconnection is the Tillery Hydro Plant Substation. This project is listed in the Duke Energy Progress interconnection queue as of June 28, 2023, with an interconnection agreement status of "Cluster Study".
The proposed project is linked to the existing Tillery Hydro Plant. It is located in the Southeast region and consists solely of hydroelectric generation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Montgomery
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Service Type
NRIS
Point of Interconnection
Tillery Hydro Plant Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
What is the total generation capacity of Duke Energy's 208 plants, broken down by energy source?
Structured data lookup for Duke Energy with rankings and aggregations.
Westminister NC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
CPG - Duke 6000 Holabird
Data-driven briefing on Duke Energy — fleet, generation, financial, and news signals.
CPG - Duke 5900 Holabird
Data-driven briefing on Duke Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.