Duke-898999
199.9 MW storage in Robeson, NC · In queue since June 2023
199.9 MW
Capacity
1
Components
Battery
3y 1m
In Queue
IA Executed
IA Phase
Total Duration
3y 1m
Study Phase
2023 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Commercial operation date not yet determined
Interconnection Agreement executed per LBNL queue status
Duke-898999 is a proposed 199.9 MW battery storage project located in Robeson County, North Carolina. The developer is masked. The project is interconnected with Duke Energy Progress and is in the Duke Energy interconnection queue, with an entry date of June 28, 2023. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Weatherspoon Plant Station.
This development project consists solely of battery storage, with a total capacity of 199.9 MW.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Robeson
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
Weatherspoon Plant Station
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-898999Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.